The Forest proposes to reauthorize PG&E's communication use lease for two passive reflectors that provide radio communication between the Pit 3 powerhouse and McCloud Dam for operation of hydroelectric facilities of FERC License #2106 project.
Location
South of McCloud Dam and reservoir, west of Hawkins Creek Road, north of Iron Canyon Reservoir on Van Sicklin Butte.
Project timeline
1
Scoping Start
07/10/2017
2
Decision
09/2017 (Estimated)
3
Implementation
09/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Shasta Trinity National Forest |
| Districts | Mt. Shasta Ranger District |
| Legal Land Description | Section 11, T.37N., R.2W., MDBM located on Van Sicklin Butte between the McCloud River drainage and the Iron Canyon Reservoir. |