Approve continued operation, maintenance and use of existing distribution and transmission powerlines and infrastructure for Pacific Gas and Electric located within designated corridors on the Shasta Trinity National Forest.
Location
Yolla Bolla, Hayfork, Big Bar, and Shasta Lake Ranger Districts
Project timeline
1
Scoping Start
03/29/2018
2
Decision
02/2019 (Estimated)
3
Implementation
03/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| PG&E Special Use Authorization Renewal Project | Decision Signed Date: 02/15/2019 |
| Forests | Shasta Trinity National Forest |
| Districts | Yolla Bolla Ranger District; Hayfork Ranger District; Big Bar Ranger District; Shasta Lake Ranger District |
| Legal Land Description | Not Applicable |