AT&T is proposing to install fiber optic cable from Lewiston, Ca. to Weaverville, Ca. Portions of the cable will be on existing Trinity Public Utilities District (TPUD) power poles, while other portions will be buried within existing road prisms.
Location
T34N, R9W in portions of Sec 26, 27, 22, 34, and 33. MDM.
Project timeline
1
Scoping Start
03/04/2019
2
Decision
03/2020 (Estimated)
3
Implementation
04/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Shasta Trinity National Forest |
| Districts | Weaverville Ranger District |
| Legal Land Description | Not Applicable |