The proponents are asking for an approved mining plan of operations for an existing mine adit as well as approval to maintain approximately 1/2 mile of road.
Location
T7N, R7E Sec 32 and 33. Humboldt Base Meridian.
Project timeline
1
Scoping Start
02/06/2020
2
Decision
08/2021 (Estimated)
3
Implementation
08/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Hazel "D" Lode Mining Plan of Operation | Decision Signed Date: 08/25/2021 |
| Forests | Shasta Trinity National Forest |
| Districts | Big Bar Ranger District |
| Legal Land Description | Not Applicable |