The Shasta-Trinity National Forest proposes to construct 1 mile of non-motorized trail near Ewing Reservoir which will connect with 10 miles of trail to be constructed on adjacent BLM-managed lands.
Location
T31N, R11W, Section 7 MDM
Project timeline
1
Scoping Start
06/01/2020
2
Decision
05/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Ewing Trail Construction Project | Decision Signed Date: 05/13/2021 |
| Forests | Shasta Trinity National Forest |
| Districts | Hayfork Ranger District |
| Legal Land Description | T31N, R11W, Section 7 MDM |