PG&E is proposing an amendment to the existing PG&E Master Special Use Permit (SUP) to permit the installation and operation of approximately 7.9 miles of new underground electric distribution lines.
Location
HWY 299 between Bidden Creek and Del Loma, N 40.794282, W -123.375998
Project timeline
1
Scoping Start
10/12/2022
2
Decision
05/2023 (Estimated)
3
Implementation
05/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Facility Improvements/Construction |
| PG&E Willow Creek Powerline Undergrounding | Decision Signed Date: 05/23/2023 |
| Forests | Shasta Trinity National Forest |
| Districts | Big Bar Ranger District |
| Legal Land Description | Not Applicable |