3.43 miles of routes would be added to the NFTS and placed on the MVUM to allow loop opportunities once testing for NOA has been completed
Location
Routes TH-41y, TH-67y, TH-3y, TH-7y, KD-219 and KD-220 in South Fork, West Fall and Dinkey-Kings Analysis Units (see MTM FEIS)
Project timeline
1
Scoping Start
10/01/2010
2
Comment Period
08/12/2012
3
Decision
09/2012 (Estimated)
4
Implementation
12/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Travel Management |
| Travel Management Decision to Include Eight Additional Routes into SNF NFTS | Decision Signed Date: 09/28/2012 Legal Notice Date: 09/30/2012 |
| Forests | Sierra National Forest |
| Districts | Sierra National Forest All Units |
| Legal Land Description | USGS Quad Numbers: 37119E6_SW (West Fall AU), 37119E7_NW (South Fork AU) , 36119H1_NW (Dinkey Kings AU) |