Ponderosa Telephone Company will be burying new fiber optic cable from the dam at Shaver Lake to the top of Musick Mtn. as they continue ti upgrade their system for increased band width and a more reliable service for customers.
Location
Adjacent to Forest Roads 9S22, 9S22A, 9S65
Project timeline
1
Scoping Start
03/07/2011
2
Decision
10/2011 (Estimated)
3
Implementation
05/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Fiber Optic Cable Installation Shaver Dam to Musick Mtn. | Decision Signed Date: 10/13/2011 |
| Forests | Sierra National Forest |
| Districts | High Sierra Ranger District |
| Legal Land Description | T9S, R24E, Sections 1, 12 |