Ponderosa Telephone Company will be burying new fiber optic cable and replacing copper cable in the Peterson Mill area as they continue to upgrade their system for increased band width and a more reliable service for customers.
Location
Peterson Mill area.
Project timeline
1
Scoping Start
03/07/2011
2
Decision
04/2014 (Estimated)
3
Implementation
06/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Peterson Mill Phone Cable Replacement and New Fiber Placement | Decision Signed Date: 04/08/2014 |
| Forests | Sierra National Forest |
| Districts | High Sierra Ranger District |
| Legal Land Description | T10S, R24E, Section 24 |