PG&E is proposing to remove dead and live hazard trees along their Haas Woodchuck 70 kilovolt transmission line. They experience outages every winter due to trees/limbs falling onto the line.
Location
Wishon Reservoir area.
Project timeline
1
Scoping Start
09/10/2012
2
Comment Period
07/19/2013
3
Decision
09/2013 (Estimated)
4
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12); 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| PG&E Haas Woodchuck Power Line Hazard Tree Removal Project | Decision Signed Date: 09/04/2013 Legal Notice Date: 11/01/2013 |
| Forests | Sierra National Forest |
| Districts | High Sierra Ranger District |
| Legal Land Description | T11S, R27E, Sections 1, 2, 11, 12, 14, 16, 22, 23, 27 |