Environmental Assessment Completed

Bass Lake Water Company Water Treatment Plant Project

Sierra National Forest Madera, California Bass Lake Ranger District

Issue a new special use permit to the Bass Lake Water Company, construct a new water treatment plant and decommission (remove) the existing water treatment plant that is no longer functioning.

Location

Bass Lake, California.

Project timeline

1
Scoping Start
06/03/2013
2
Comment Period
02/24/2015
3
Objection Period Start
04/13/2015
4
Decision
03/2016 (Estimated)
5
Implementation
04/2016 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
Bass Lake Water Company Water Treatment Plant ProjectDecision Signed Date: 03/28/2016
ForestsSierra National Forest
DistrictsBass Lake Ranger District
Legal Land DescriptionTownship 7 South, Range 22 East, Section 9, MDBM
Special use management