The purpose of the project is to capture the economic value and benefit of the forest products, and reforest the landscape deforested by the Aspen Fire.
Location
The Aspen Project area is approximately 22,350 acres and is bounded by the San Joaquin River, West; Kaiser Wilderness, East; Road 6S02, North; and Ordinance Creek, South.
Project timeline
1
Scoping Start
09/04/2013
2
Decision
06/2014 (Estimated)
3
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Noxious Weed Treatments; Road Maintenance; Timber Sales (Salvage) |
| Alternative 2 of the Aspen Recovery and Reforestation Project EA | Decision Signed Date: 06/27/2014 |
| Forests | Sierra National Forest |
| Districts | High Sierra Ranger District |
| Legal Land Description | all or portions of: Township 6 South, Range 24 East; T7S, R24E; T8S, R24E; T6S, R25E; and T7S, R25E ; Mount Diablo Base Meridian. |