The project would remove roadside hazard trees, recover the economic value of fire-killed/ fire-damaged trees, re-establish forested conditions, manage fuel loads, and work towards eradication of invasive non-native weeds.
Location
Includes the lands immediately north of Clearwater Creek, south of West Fork Chiquito Creek, east of Whisky Ridge, and west of the San Joaquin River
Project timeline
1
Scoping Start
10/30/2014
2
Decision
08/2015 (Estimated)
3
Implementation
09/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Noxious Weed Treatments; Road Maintenance; Timber Sales (Salvage) |
| French Fire Recovery and Reforestation Project | Decision Signed Date: 08/26/2015 |
| Forests | Sierra National Forest |
| Districts | Bass Lake Ranger District |
| Legal Land Description | Township 6 Range 24 Section 33; Township 7 Range 24 Sections 3-11, 14-22, 26-30, 32-35; Township 8 South Range 24 Sections 2-5, 8-11, 16, & 15, Mount Diablo Base Meridian. |