Fresno/Madera Counties are proposing to replace Italian Bar Bridge crossing the San Joaquin River. The existing bridge is 241 feet long and 12 feet wide between the railings and is classified as both structurally deficient and functionally obsolete.
Location
Italian Bar Bridge crossing the San Joaquin River / Redinger Lake near SCE Powerhouse #3.
Project timeline
1
Scoping Start
08/21/2017
2
Comment Period
10/03/2017
3
Decision
12/2017 (Estimated)
4
Implementation
04/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations; Road Improvements/Construction |
| SUP Issuance for the Italian Bar Road Bridge Replacement Prjt Construction | Decision Signed Date: 12/19/2017 |
| Forests | Sierra National Forest |
| Districts | Sierra National Forest All Units |
| Legal Land Description | Not Applicable |