Environmental Assessment Completed

Camp Project

Tahoe National Forest Nevada; Sierra; Yuba, California Yuba River Ranger District

Improve forest health, watershed health and wildlife habitat, and reduce surface fuel loadings and ladder fuels to a level that would allow safe fire suppression

Location

West and north of the community of Camptonville and east and north of Bullards Bar Reservoir

Project timeline

1
Scoping Start
08/02/2012
2
Comment Period
03/25/2013
3
Decision
05/2013 (Estimated)
4
Implementation
07/2013 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Road Maintenance; Timber Sales (Green); Watershed Improvements
Camp Project DN/FONSIDecision Signed Date: 05/06/2013 Legal Notice Date: 05/09/2013
ForestsTahoe National Forest
DistrictsYuba River Ranger District
Legal Land DescriptionT18N R7E Sections 24-26; R8E Sections 2-11, 15-22 and 27-33; T19N R7E Sections 13, 24-26, and 35-36; R8E Sections 7-9, 11, and 13-36; R9E Section 19
Fuels managementWildlife, fish, rare plantsVegetation management (other than forest products)Forest productsWatershed management