Forest Service is a cooperating agency with FERC to prepare the environmental analysis for this project. Forest Service proposal is to issue an SUP to PG&E for the use and improvement of the following FS roads: 85, 85-2, and 85-2-1.
Location
Lake Fordyce
Project timeline
1
Scoping Start
11/27/2019
2
Comment Period
01/14/2021
3
Decision
03/2021 (Estimated)
4
Implementation
05/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| PG&E Lake Fordyce Dam Seepage Mitigation Project | Decision Signed Date: 03/10/2021 |
| Forests | Tahoe National Forest |
| Districts | Yuba River Ranger District |
| Legal Land Description | T 17N, R 13E, Sections 10, 16, and 20 |