The project proposes (OHV) and Watershed Improvement management actions on National Forest System lands including changes to the NFTS, realignment, decommission and restoration of routes, construction of motorized trail, and staging area creation.
Location
Boca, Stampede, and Prosser Reservoirs area adjacent to the 890, 894, 270, and 72 Rd. systems. Project also encompasses the 06 Rd. in the vicinity of the Big Chief cliff complexes north of Deer Creek.
Project timeline
1
Scoping Start
04/03/2020
2
Comment Period
09/04/2020
3
Objection Period Start
12/18/2020
4
Decision
03/2021 (Estimated)
5
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Developed Site Management; Trail Management; Road Maintenance; Road Improvements/Construction; Watershed Improvements |
| East Zone Connectivity and Restoration Project | Decision Signed Date: 03/15/2021 |
| Forests | Humboldt-Toiyabe National Forest; Tahoe National Forest |
| Districts | Carson Ranger District; Truckee Ranger District |
| Legal Land Description | T 19,18,17,and 16 N - R 17 and 16 E - Covering more than 40 sections in Nevada, Sierra, and Placer counties. |