Decision Memo Completed

Carvin Creek Electrical Line

Tahoe National Forest Sierra, California Yuba River Ranger District

Construction of a new underground electrical line measuring 99 feet long, 1 foot wide, 2 feet deep to install conduit and wiring to provide reliable, safe drinking water to the cabins at the Carvin Creek Summer Home Tract.

Location

Carvin Creek Summer Home Tract. T21N, R13E.

Project timeline

1
Scoping Start
07/24/2024
2
Decision
08/2024 (Estimated)
3
Implementation
08/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
Carvin Creek Electrical LineDecision Signed Date: 08/13/2024
ForestsTahoe National Forest
DistrictsYuba River Ranger District
Legal Land DescriptionNot Applicable
Special use management