Issue a temporary construction permit for well site #1 and associated conduit and pipe connecting the well to existing facilities.
Location
Adjacent to existing permitted facilities within the Sierraville ranger district at Sieraville Public Utilities District site at Railroad Springs.
Project timeline
1
Scoping Start
01/08/2025
2
Decision
02/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Sieraville Public Utilities Well Construction | Decision Signed Date: 02/11/2025 |
| Forests | Tahoe National Forest |
| Districts | Sierraville Ranger District |
| Legal Land Description | NW� of the NE� of Section 25, Township 20 North, Range 14 East, Mount Diablo Meridian. |