Project timeline

1
Scoping Start
04/18/2012
2
Comment Period
04/18/2012
3
Decision
05/2013 (Estimated)
4
Implementation
06/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
USGS Newport Geophysical Observatory Waterline Extension/Fire Hydrant InstaDecision Signed Date: 05/31/2013 Legal Notice Date: 05/31/2013
ForestsColville National Forest
DistrictsNewport Ranger District
Legal Land DescriptionT32N, R45E, Sec. 21