Restore the banks & floodplain of Lambert Cr. & the existing campground area. Includes relocating the campground loop rd., campsite turnouts, & utilizing woody debris & rocks to rehabilitate the creek, floodplain, and effected campground area
Location
FS Road 2156-000 The project is located within the Lambert Creek watershed
Project timeline
1
Scoping Start
02/25/2015
2
Decision
08/2015 (Estimated)
3
Implementation
09/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Developed Site Management; Road Improvements/Construction; Watershed Improvements |
| Lambert Restoration Project | Decision Signed Date: 08/05/2015 |
| Forests | Colville National Forest |
| Districts | Republic Ranger District |
| Legal Land Description | T37N R34E SW1/4 of Section 4, |