The Timber Mountain proposed action will be based on direction found within the Colville National Forest Land and Resource Management Plan (Forest Plan, 1988) as amended by the continuation of Interim Management Direction.
Location
The analysis area is within the Ruby Creek and Lost Creek subwatersheds. Primary access is via Ruby Creek Road (2700, 2712)
Project timeline
1
Scoping Start
05/01/2015
2
Comment Period
06/15/2016
3
Objection Period Start
09/13/2016
4
Decision
11/2016 (Estimated)
5
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| Timber Mountain Vegetation Management Project | Decision Signed Date: 11/08/2016 |
| Forests | Colville National Forest |
| Districts | Sullivan Lake Ranger District |
| Legal Land Description | Not Applicable |