Danger tree removal, salvage of selected danger trees, reforestation and road closures within the Egley Fire Complex.
Location
Egley Fire Complex
Project timeline
1
Scoping Start
04/17/2008
2
Comment Period
07/23/2008
3
Decision
09/2008 (Estimated)
4
Implementation
09/2009 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Road Maintenance; Timber Sales (Salvage) |
| Egley Fire Restoration Project Decision Notice and FONSI | Decision Signed Date: 09/08/2008 Legal Notice Date: 09/10/2008 |
| Forests | Malheur National Forest |
| Districts | Emigrant Creek Ranger District |
| Legal Land Description | T19S, R25E, T19S, R26E, T19S, R27E, T19S, R28E, T20S, R25E, T20S, R26E, T20S, R27E, T20S, R28E, T20S, R29E, T21S, R25E, T21S, R26E, T21S, R27E, T21S, R28E, T22S, R28E |