Develop JB spring for livestock and wildlife use. Install a steel headbox, livestock water trough and thin approximately 5 acres of small juniper that have encroached into the spring area.
Location
JB Spring
Project timeline
1
Scoping Start
04/27/2011
2
Decision
08/2011 (Estimated)
3
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management |
| Decision Memo J B Spring Development | Decision Signed Date: 08/22/2011 |
| Forests | Malheur National Forest |
| Districts | Emigrant Creek Ranger District |
| Legal Land Description | T19S, R33E, Section 13, SW1/4 SE 1/4 |