Project timeline
1
Scoping Start
08/31/2011
2
Objection Period Start
05/09/2012
3
Decision
06/2012 (Estimated)
4
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| DN, FONSI, AND FPA #70 for Marshall Devine Hazardous Fuel Reduction Project | Decision Signed Date: 06/20/2012 |
| Forests | Malheur National Forest |
| Districts | Emigrant Creek Ranger District |