1
Scoping Start
03/26/2014
2
Comment Period
08/27/2014
3
Objection Period Start
04/08/2015
4
Decision
09/2015 (Estimated)
5
Implementation
10/2015 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Developed Site Management; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Special Products Sales; Road Maintenance; Road Improvements/Construction; Grazing Structural Improvements; Timber Sales (Green); Watershed Improvements
Big Mosquito Project Decision Notice and FONSIDecision Signed Date: 09/30/2015