The Magone Project includes a suite of activities to restore forest resiliency, including silviculture and fuels treatments, Magone Lake restoration, recreation developments, and associated road activities.
Location
Township 11S Range 31E Sections 25-29, 32-36; Township 11S Range 32E Sections 30-32; Township 12S Range 31E Sections 1-5, 8-12, 13-15, 17-24; Township 12S Range 32E Sections 5-11, 15-20, All in the Willamette Meridian.
Project timeline
1
NOI in Federal Register
02/13/2015
2
DEIS NOA in Federal Register
02/05/2016
3
FEIS NOA in Federal Register
12/28/2016
4
Objection Period Start
12/28/2016
5
Decision
05/2017 (Estimated)
6
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Developed Site Management; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Trail Management; Special Products Sales; Road Maintenance; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Magone | Decision Signed Date: 05/01/2017 |
| Forests | Malheur National Forest |
| Districts | Blue Mountain Ranger District |
| Legal Land Description | Not Applicable |