Decision Memo Completed

BLM Use of Snow Mountain Communication Site

Malheur National Forest Grant, Oregon Emigrant Creek Ranger District

Install a BLM repeater integration system on a Forest Service communication tower, with equipment, at the Snow Mountain repeater site.

Location

Snow Mountain repeater site in Sec. 32, T. 18 S., R. 27 E.

Project timeline

1
Scoping Start
04/05/2016
2
Decision
06/2016 (Estimated)
3
Implementation
06/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
BLM Use of Snow Mountain Communication SiteDecision Signed Date: 06/08/2016
ForestsMalheur National Forest
DistrictsEmigrant Creek Ranger District
Legal Land DescriptionNot Applicable
Special use management