Bury two existing overhead distribution lines for the reduction of fire start risk on ECRD.
Location
Two locations off 69 kV line to Crow Flat Guard Station and private property.
Project timeline
1
Scoping Start
08/19/2020
2
Decision
08/2020 (Estimated)
3
Implementation
09/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| OTEC Bury Overhead Powerlines | Decision Signed Date: 08/26/2020 |
| Forests | Malheur National Forest |
| Districts | Emigrant Creek Ranger District |
| Legal Land Description | T. 20 S., R. 31 E., Sections 13 and 23 |