Verizon Wireless to add 65' X 9' of new solar panels (15 panel sections) to the existing communication sites solar power system.
Location
Aldrich Mountain communication site
Project timeline
1
Scoping Start
06/29/2020
2
Decision
04/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Verizon Solar Panel at Aldrich Communication Site | Decision Signed Date: 04/22/2021 |
| Forests | Malheur National Forest |
| Districts | Blue Mountain Ranger District |
| Legal Land Description | Section 11, T. 14 S., R. 27 E., Willamette Meridian |