Decision Memo Completed

Verizon Solar Panel at Aldrich Communication Site

Malheur National Forest Grant, Oregon Malheur National Forest All Units

Verizon Wireless to add 65' X 9' of new solar panels (15 panel sections) to the existing communication sites solar power system.

Location

Aldrich Mountain communication site

Project timeline

1
Scoping Start
06/29/2020
2
Decision
04/2021 (Estimated)
3
Implementation
06/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
Verizon Solar Panel at Aldrich Communication SiteDecision Signed Date: 04/22/2021
ForestsMalheur National Forest
DistrictsBlue Mountain Ranger District
Legal Land DescriptionSection 11, T. 14 S., R. 27 E., Willamette Meridian
Special use management