Project timeline
1
Scoping Start
09/21/2009
2
Comment Period
09/21/2009
3
Decision
04/2010 (Estimated)
4
Implementation
06/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning |
| Zigzag Road Decommissioning for Habitat Restoration, Increment 2 | Decision Signed Date: 04/05/2010 |
| Forests | Mt. Hood National Forest |