Decision Memo · Clackamas River Ranger District · updated 4/13/2026
Section 08, T6S, R7E · Clackamas, Oregon
PGE needs rock material to conduct road maintenance per agreement with their FERC license for the Clackamas River Hydro Project. Therefore, the purpose of this project is to issue a permit to PGE to extract rock material from an existing quarry.
Special use management
Decision
11/2025 (Estimated)
Implementation
01/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Mt. Hood National Forest All Units · updated 4/13/2026
On National Forest System lands within the existing RLK & Co. special use permit boundary and an adjacent, less than 1-acre area (at Summit Pass), where a permit boundary adjustment is proposed. · Clackamas, Oregon
Gondola construction at Summit Pass for access near Timberline Lodge; improvements for skier connectivity, circulation, and beginner skiers; and Summit Pass base area reconfiguration for parking, guest service capacity, and a transit hub.
Special use management
NOI in Federal Register
01/2026 (Estimated)
DEIS NOA in Federal Register
10/2026 (Estimated)
FEIS NOA in Federal Register
08/2027 (Estimated)
Objection Period Start
08/2027 (Estimated)
Decision
10/2027 (Estimated)
Implementation
10/2027 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 2/12/2026
Various areas on the east side of the Mt Hood National Forest. See attached map. · Hood River; Wasco, Oregon
Small diameter (8-10") noncommercial tree thinning, pruning, brushing and burning on approximately 10,000 acres.
Vegetation management (other than forest products)Fuels management
Decision
07/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District; Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 9/18/2025
The underground line would run along the existing powerline corridor to the Upper Bowl chairlift at Skibowl and then along the maintenance road to existing communication site. · Clackamas, Oregon
There is a need for a more dependable wireless network throughout the broadcast corridor provided by the communication site at Skibowl. This project would install approximately 1.3 miles of underground fiber optic within an existing utility corridor.
Special use management
Decision
07/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Section 23, 24, and 26; T3N, R8E |
Decision Memo · Zigzag Ranger District · updated 6/26/2025
Section 14, T3S, R7E · Clackamas, Oregon
A portion of Forest Service road 20e is no longer useable for accessing Lady Creek Water System's pressure station; therefore, there is a need to repair this road. Also, there is a need to replace unserviceable buried water pipes near the road.
Special use management
Decision
05/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 6/26/2025
Community of Government Camp and Timberline Lodge · Clackamas, Oregon
As part of PGE's Wildfire Mitigation Plan, there is a need to minimize wildland fire risk associated with utilities in the National Forest. Therefore, this project would underground approximately 5 miles of existing powerline.
Special use management
Decision
06/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 6/26/2025
Flag Point Communications Site · Wasco, Oregon
There is a need to cover gaps in communication services between the rural communities of Dufur, Friend, Maupin, Pine Grove, Pine Hollow, Tygh Valley, and Wamic. This project would add telecommunications to the communication site at Flag Point.
Special use management
Decision
05/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Section 07, T03S, R11E |
Decision Memo · Hood River Ranger District · updated 6/18/2025
Indian Mountain Communications Site · Hood River, Oregon
A repeater would be installed at the Indian Mountain Communications Site in order to improve radio communication for the Hood River County Sheriff's Office. The repeater would enhance the mission readiness of search and rescue efforts in the region.
Special use management
Decision
05/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Section 21, T1N, R8E |
Decision Memo · Mt. Hood National Forest All Units · updated 6/18/2025
Ski Areas: Timberline Complex; Mt. Hood Meadows; Skibowl; Cooper Spur; and Teacup · Clackamas; Hood River, Oregon
Ski areas have ongoing repair and maintenance needs to meet Forest Service standards. This project allows for ski areas to better maintain existing utilities within permitted areas.
Special use management
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Electric Transmission; Special Use Authorizations; Facility Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District; Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 4/22/2025
Recreation residence tract on the Zigzag Ranger District. · Clackamas, Oregon
PGE is legislatively mandated to remove power line attached to trees. Therefore, PGE is proposing to remove approximately 250 electrical distribution lines from trees. This activity would require modification to the existing right of way.
Special use management
Decision
04/2025 (Estimated)
Implementation
05/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Hood River Ranger District · updated 3/27/2025
FSR 1300-000 · Hood River, Oregon
The purpose of the project is to conduct road work necessary to reopen Forest System Road (FSR) 1300-000 to the public as a Maintenance Level 2 road.
Road management
Decision
03/2025 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 3/6/2025
Timberline Special Use Permit Area · Clackamas, Oregon
The project would involve trenching to install three new night lighting extensions and one new snowmaking power extension within the Special Use Permit Area of Timberline.
Special use management
Decision
03/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Timberline Pucci Night Lighting and Buzz Cut Snowmaking Power Extensions | Decision Signed Date: 03/05/2025 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 12/24/2024
Mt. Hood SkiBowl Ski Area Permit Area · Clackamas, Oregon
Construct an additional 2 miles of downhill mountain bike trails within the Mt. Hood SkiBowl permit boundary. The proposed trail would go from the Upper Bowl Chairlift to Lower Bowl Chair area. Some of the trail would be within existing roads.
Recreation managementSpecial use management
Decision
07/2015 (Estimated)
Implementation
07/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Trail Management |
| SkiBowl Mountain Bike Trail | Decision Signed Date: 07/14/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 9/30/2024
The project is in the southeastern portion of the Barlow Ranger District, near Rock Creek Reservoir. · Wasco, Oregon
This project will rehabilitate Roads 4800-020, 4800-170 and 3530-000 by installing ditches, culverts, and surfacing roads as needed.
Road management
Scoping Start
07/2024 (Estimated)
Decision
08/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T 4S, R 11E, Sections 25, 26, 34, 35 |
Decision Memo · Hood River Ranger District · updated 9/6/2024
Mt Hood Meadows · Hood River, Oregon
The project will cut five trees in the Mt Hood Meadows special use permit area.
Facility management
Decision
08/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Hood River Ranger District · updated 8/5/2024
The project area is located east of OR Route 35 and north of the Dalles Watershed Management unit. · Hood River; Wasco, Oregon
The primary purposes of this project are to reduce the risk of landscape level disturbance and increase forest resiliency to insect and disease.
Climate change adaptationFuels managementVegetation management (other than forest products)Forest products
Decision
07/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T 1 S, R 10 E, S 1,2,11,12,13,14,15,22,23; T 1 S, R 11 E, S 5,6,7,18 |
Decision Memo · Mt. Hood National Forest All Units · updated 7/18/2024
Within the Mt. Hood Meadows special use permit area. · Hood River, Oregon
Construct approximately 1.6 miles of new hiking trail within the Mt. Hood Meadows special use permit area.
Special area management
Decision
11/2022 (Estimated)
Implementation
04/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 6/6/2024
Barlow Ranger District · Wasco, Oregon
This project would manage dense and dying vegetation within and around the ANPO special uses permit area.
Vegetation management (other than forest products)Fuels managementSpecial use management
Decision
06/2024 (Estimated)
Implementation
11/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (14), 36 Cfr 220.6(E)(14) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Township 4 South, Range 11 East |
Decision Memo · Mt. Hood National Forest All Units · updated 4/18/2024
Various locations on Barlow and Hood River Districts. · Hood River; Wasco, Oregon
This project would decommission eleven toilets that have degraded beyond repair.
Facility management
Decision
04/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Dispersed Recreation Mgmt. |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 4/3/2024
Clear Branch Dam · Hood River, Oregon
Middle Fork Irrigation District (MFID), in partnership and cooperation with the Natural Resources Conservation Service (NRCS) and Forest Service, propose to drill three boreholes at Clear Branch Dam on the downstream face of the dam.
Facility managementSpecial use managementResearch
Decision
04/2024 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Facility Maintenance; Research And Development |
| Decision Decided Date | 04/03/2024 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 1/30/2024
The planning area is located along NFS Roads 2700000, 2710000, 2720000, 2730000 and 4421000. · Wasco, Oregon
The primary purpose of this project is to reduce the risk of landscape level disturbance by establishing a linear fuel break along National Forest System (NFS) roads.
Forest productsFuels managementClimate change adaptationVegetation management (other than forest products)
Decision
01/2024 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T2S, T3S, T4S, R11E, R12E |
Decision Memo · Barlow Ranger District · updated 1/23/2024
Hidden Meadows Trail · Wasco, Oregon
The purpose of this project is to extend the Hidden Meadows Trail (#472) to connect to the Crane Creek Trail (#478). There is a need to build a system trail connector to reduce visitor impacts to aquatic and other resources.
Recreation management
Decision
01/2024 (Estimated)
Implementation
03/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 1/11/2024
NFS Road 3530000 at the White River · Wasco, Oregon
The purpose of the project is to replace an existing bridge along National Forest System Road 3530000 (the Historic Barlow Road) at the White River.
Road management
Decision
01/2024 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Heritage Resource Management; Facility Maintenance; Road Maintenance; Special Area Management; Travel Management |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T4S, R10E, Sec 30, 31 |
Decision Memo · Hood River Ranger District · updated 11/7/2023
All project activities will occur within the Lost Lake Resort permit area. · Hood River, Oregon
This project would replace cabins #1 and #7 as well as a vault toilet at Lost Lake Resort.
Special use managementFacility managementRecreation managementHeritage resource management
Decision
10/2023 (Estimated)
Implementation
11/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Heritage Resource Management; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T 1 S., R. 8 E., Sec. 10 |
Decision Memo · Hood River Ranger District · updated 11/7/2023
Pocket Creek Ski Trail System · Hood River, Oregon
The project will replace four trail bridges in the Pocket Creek ski trail system.
Recreation managementFacility management
Decision
11/2023 (Estimated)
Implementation
05/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T. 3 S., R. 9 and 10 E |
Decision Memo · Hood River Ranger District · updated 10/3/2023
Mt. Hood Meadows Ski Resort · Hood River; Wasco, Oregon
This project will replace the above-ground, RFID gate gantries, at Buttercup, Cascade, and Shooting Star lifts, with inground installations that match the other lifts in the resort.
Facility managementRecreation management
Decision
09/2023 (Estimated)
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 9/27/2023
East Fork Trail (#650) at Cold Spring Creek (45.404293, -121.570975) and Elk Cove Trail (#631) at Pinnacle Creek (45.446833, -121.677481) · Hood River, Oregon
The project will replace two trail bridges along two existing trails.
Recreation managementFacility management
Decision
02/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 9/19/2023
East of Rhododendron, off North side of HWY 26 · Clackamas, Oregon
Lady Creek Water system proposed to drill up to three additional wells, in order to meet current and future needs.
Special use management
Decision
09/2023 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S, R8E, section 16 |
Decision Memo · Hood River Ranger District · updated 6/12/2023
Project is located within the Lost Lake Resort area. · Hood River, Oregon
This project will dig a test well within the permit area of Lost Lake Resort in order to identify options for a water system upgrade.
Recreation managementMinerals and geologySpecial use management
Decision
05/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T. 1 S, R. 8 E, Section 10 |
Decision Memo · Barlow Ranger District · updated 4/28/2023
The project area is bordered to the west by Forest System Road (FSR) 4811000; to the north by the Souva Creek drainage; and to the south by the FSR 4800000. · Wasco, Oregon
This project will reduce the risk of landscape-level disturbance and increase forest resiliency to insect and disease. Vegetation treatments would take place on less than 3,000 acres in the southeastern portion of the Barlow Ranger District.
Forest productsVegetation management (other than forest products)Climate change adaptationFuels management
Decision
04/2023 (Estimated)
Implementation
05/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Township 4 South, Range 10 East, Section24; and Township 4 South, Range 11 East, Sections 19, 20, 21, 22, 27, 28, 29, 30, 32, 33, and 34. |
Decision Memo · Mt. Hood National Forest All Units · updated 4/19/2023
Teacup Lake Sno-Park, north and south entrances; Pocket Creek Sno Park at FSR 3540-000; Skyline Sno-Park at FSR 4200-000; FSR 4400-000 at OR Hwy. 35; FSR 5800-000 at 5830-000. · Clackamas; Hood River; Wasco, Oregon
This project will install six gates at six locations. There is a need for gates at these locations to enforce seasonal (winter) closures to vehicles over 48 inches wide. These roads are only open to either skiing or snowmobile use in the winter.
Road managementFacility managementRecreation management
Decision
04/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Dispersed Recreation Mgmt.; Facility Maintenance; Travel Management |
| Decision Decided Date | 04/19/2023 |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 3/31/2023
Rim Rock Trail (#487A) and McCubbins Gulch OHV Trail (#592) · Wasco, Oregon
The purpose of this project is to realign a segment of the Rim Rock Trail (#487A) and move a segment of the McCubbins Gulch OHV Trail (#592) outside of Wilderness. Both projects will move the trails out of areas impacted by fire.
Projects that may affect wilderness (for mailing list contacts)Recreation management
Decision
03/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Wilderness Management |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Hood River Ranger District · updated 3/6/2023
Barlow Creek Bridge on NFS Road 3530000 · Wasco, Oregon
This project will replace the failed bridge on the historic Barlow Road (NFS Road 3530000).
Road management
Decision
03/2023 (Estimated)
Implementation
04/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Heritage Resource Management; Facility Maintenance; Road Maintenance; Travel Management |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.4S., R.9E., S.13 |
Environmental Assessment · Barlow Ranger District · updated 1/11/2023
The planning area is south of the Badger Creek Wilderness and east of NFS Road 4880. The eastern border is near Bonney Crossing Campground. The southern border is near the Wasco/Hood River County line · Hood River; Wasco, Oregon
The Grasshopper project intends to enhance and restore forest diversity; reduce risks associated with high-intensity wildfires; improve conditions for wildlife and aquatic resources; and provide timber and other forest products.
Wildlife, fish, rare plantsForest productsVegetation management (other than forest products)Fuels management
Comment Period
02/18/2022
Objection Period Start
09/02/2022
Decision
01/2023 (Estimated)
Implementation
03/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.3N.,R.10E.;T.3N.,R.11E.;T.4N.,R.10E..;T.4N.,R.11E.; |
Decision Memo · Barlow Ranger District · updated 11/29/2022
Approixmately one acre adjacent to NFS Road 1700690 · Hood River, Oregon
This project will create a staging area approximately one acre in size to facilitate pipeline replacement activities.
Special use managementFacility management
Decision
11/2022 (Estimated)
Implementation
04/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.2S., R.10E., S.3 |
Decision Memo · Hood River Ranger District · updated 11/21/2022
White River West Sno Park, White River East Sno Park, Bennett Pass, Polallie Trailhead · Hood River, Oregon
This project will install new toilets at White River West Sno Park, White River East Sno Park, Bennett Pass, and Polallie Trailhead. A toilet building will be moved from Bennett Pass to Polallie Trailhead.
Recreation managementFacility management
Decision
11/2022 (Estimated)
Implementation
04/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Facility Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Mt. Hood National Forest All Units · updated 11/9/2022
The new communication facility (tower and associated infrastructure) would be located on the Hood River Ranger District off of National Forest System (NFS) Road 4400630, east of Highway 35. · Hood River, Oregon
Construction of a new communication facility (a tower and associated infrastructure) to provide FirstNet coverage to first responders and improved wireless coverage to those in the area.
Special use management
Comment Period
06/09/2022
Objection Period Start
09/14/2022
Decision
11/2022 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T02S, R10E, Section 9. |
Decision Memo · Mt. Hood National Forest All Units · updated 10/24/2022
The project is located at the intersection of the Dog River Trail (#675) and Puppy Creek. · Hood River, Oregon
This project will replace a bridge on the Dog River Trail at the Puppy Creek crossing.
Facility managementRecreation management
Decision
10/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Trail Management |
| Decision Decided Date | 10/24/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.1 S., R.10 E., Section 21 |
Decision Memo · Zigzag Ranger District · updated 10/19/2022
Timberline Communication Site · Clackamas, Oregon
The Clackamas Radio Group 800 requested to bury a propane tank as their secondary power source at the Timberline Communication Site.
Special use management
Decision
10/2022 (Estimated)
Implementation
11/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Mt. Hood National Forest All Units · updated 10/14/2022
Within portions of the Riverside, Lionshead, and Bull Complex Fires that overlap the Mt. Hood National Forest. · Clackamas; Jefferson; Marion, Oregon
The purpose of this project is to do an assessment of fire-caused safety and access issues so that roads can either be safely opened for public and administrative access, closed with effective barriers, or decommissioned.
Vegetation management (other than forest products)Road management
Comment Period
04/27/2022
Objection Period Start
07/15/2022
Decision
09/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Road Maintenance; Travel Management |
| Clackamas Fires Roadside Danger Tree Project | Decision Signed Date: 09/26/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 10/11/2022
Inside ODOT Bennett Pass storage yard and south of storage yard fence line. · Hood River, Oregon
The purpose of this project is to amend an existing special use permit held by Teacup Lake Nordic Club to clear a new groomer path and construct a new groomer shed.
Special use managementFacility management
Decision
10/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Township 3 South, Range 9 East, Section 11. |
Decision Memo · Mt. Hood National Forest All Units · updated 9/12/2022
Troutdale airport · Multnomah, Oregon
The area contains approximately 9.65 acres and is located at 503 NW Graham Road, City of Troutdale, Oregon. The property consists of two buildings and taxiway. The Troutdale Air Tanker Base is currently closed to all air tanker operations.
Land ownership management
Decision
09/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Use Adjustments |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T. 1 N., R. 3 E., Sections 23 and 24,Portion of Lewis Marr Donation Land Claim No. 45. |
Decision Memo · Mt. Hood National Forest All Units · updated 8/31/2022
Lower Twin Lake · Hood River, Oregon
This project will install one decomposting toilet in this high-use, backcountry recreation area.
Facility managementRecreation management
Decision
08/2022 (Estimated)
Implementation
09/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 08/31/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.4.S., R.9.E., section 9 |
Decision Memo · Hood River Ranger District · updated 7/20/2022
Mt. Hood Meadows Ski Area Special Use Permit Area · Hood River, Oregon
The project will install five gates inside the Mt. Hood Meadows permit area to ensure security of privately owned infrastructure.
Special use managementRoad managementFacility management
Decision
07/2022 (Estimated)
Implementation
07/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Facility Maintenance |
| Decision Decided Date | 07/20/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T3S; R9E |
Decision Memo · Barlow Ranger District · updated 7/20/2022
near High Prairie Trailhead parking area. · Hood River, Oregon
The purpose of the project is to amend an existing special use permit held by the Natural Resources Conservation Service (NRCS) to install a new SNOTEL weather station located in the Mt. Hood National Forest.
Climate change adaptationSpecial use managementResearch
Decision
07/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Research And Development |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Township 2 South, Range 10 East, Sections 34, 35. |
Decision Memo · Hood River Ranger District · updated 5/24/2022
A Frame at Lost lake Campground · Hood River, Oregon
This project will conduct activities to install a solar panel array and components at the A-Frame site at Lost Lake Campground. This will provide a safer and more efficient lighting system for recreationists.
Facility managementSpecial use management
Decision
05/2022 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations; Facility Maintenance |
| Decision Decided Date | 05/24/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.1.N.,R.71/2.E.,section 10. |
Environmental Impact Statement · Mt. Hood National Forest All Units · updated 5/6/2022
Government Camp, Oregon, and Cooper Spur area, Oregon · Clackamas; Hood River, Oregon
The Forest Service would convey acreage near Government Camp for acreage of private land near Cooper Spur. This land exchange was mandated by Congress in the Omnibus Public Land Management Act of 2009.
Land ownership management
NOI in Federal Register
02/16/2016
DEIS NOA in Federal Register
10/28/2016
FEIS NOA in Federal Register
02/05/2021
Objection Period Start
02/05/2021
Decision
05/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Land Exchanges |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District; Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 5/2/2022
Barlow Ranger District · Wasco, Oregon
The project would mechanically thin, masticate, pile, and brush sapling plantations on 1,340 acres on the Barlow Ranger District within the footprint of the 2010 TSI planning area.
Vegetation management (other than forest products)Fuels management
Decision
05/2022 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T02S R11E, T03S R10E, and R11E, and T04S R10E, and R11E. Willamette Meridian. |
Decision Memo · Clackamas River Ranger District · updated 4/26/2022
Within areas burned by the Bull Complex Fire on the Clackamas River Ranger District. · Clackamas; Marion, Oregon
Reforest areas burned by the Bull Complex Fire on the Clackamas River Ranger District.
Vegetation management (other than forest products)
Decision
04/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 4/20/2022
The project area is bordered to the west by Forest Road 4430; to the east by the Forest boundary, to the north by Forest Roads 1720 and 4431; and to the south by the Eightmile Creek drainage. · Wasco, Oregon
This project will reduce the risk of landscape-level disturbance and increase forest resiliency to insect and disease. Vegetation treatments would take place on less than 3,000 acres in the eastern portion of the Barlow Ranger District.
Fuels managementForest productsVegetation management (other than forest products)
Decision
04/2022 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T1S, R10E, Section 36. T2S, R10E, Sections 1 and 12. T1S, R11E, Sections 23, 24, 25, 26, 27, 31, 32, 33, 34, 35, and 36; and T2S, R11E, Sections 2, 3, 4, 5, 6, 7, 8, 9, 10, and 11. |
Decision Memo · Barlow Ranger District · updated 4/11/2022
along National Forest System (NFS) roads within the perimeter of or adjacent to the White River Fire · Wasco, Oregon
This project aims to mitigate risks associated with damaged and defective trees along National Forest System (NFS) roads within the perimeter of or immediately adjacent to the White River Fire.
Road management
Decision
08/2021 (Estimated)
Implementation
08/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Travel Management |
| White River Fire Roadside Danger Tree Abatement | Decision Signed Date: 08/10/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T4.S.-R.9E,R.10E,R.11E(multiple sections); T5.S.-R.9E,R.10E,R.11E(multiple sections) |
Decision Memo · Zigzag Ranger District · updated 3/24/2022
Timberline Lodge ski area, south face of Mt. Hood, 60 miles east of Portland, OR. · Hood River, Oregon
Timberline Lodge and Ski Area requests Alpine Trail selective tree removal, Molly's Trail enhancements, and Pucci lights upgrade. All components of the project fall within the Timberline and Summit Ski Area Special Use Permit areas.
Recreation managementSpecial use management
Decision
03/2022 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations; Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Clackamas River Ranger District · updated 3/17/2022
Sourth Fork Clackamas River and Clear Creek · Clackamas, Oregon
Thinning second-growth stands on approximately 2,800 acres of mid-aged stands ranging in age from 30 to 60 years old in parts of the Middle Clackamas, Lower Clackamas, and Lower Molalla River Watersheds.
Forest products
Comment Period
01/29/2016
Objection Period Start
06/22/2016
Decision
09/2016 (Estimated)
Implementation
11/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Mt. Hood National Forest All Units · updated 1/10/2022
Collawash River, Eagle Creek, East Fork Hood River, Fifteenmile Creek, Fish Creek, Middle Fork Hood River, South Fork Clackamas River, South Fork Roaring River, and Zigzag River · Clackamas; Hood River; Multnomah; Wasco, Oregon
The purpose of this comprehensive river management plan is to establish management direction to protect and enhance the river values for nine rivers designated in 2009. The plan establishes river corridor boundaries, user capacities and monitoring.
Recreation managementSpecial area managementWatershed managementWildlife, fish, rare plantsLand management planning
Comment Period
02/19/2021
Objection Period Start
09/10/2021
Decision
01/2022 (Estimated)
Implementation
02/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Plan Amendment; Special Area Management |
| Wild and Scenic River CRMP for Nine Wild and Scenic Rivers | Decision Signed Date: 01/10/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Hood River Ranger District · updated 12/14/2021
Mt. Hood Meadows Ski Resort, Mount Hood, Oregon · Hood River, Oregon
The Mt. Hood Express chairlift at Mt. Hood Meadows Ski Resort is proposed to be replaced within the existing corridor with newer chairlift technology.
Special use managementRecreation management
Decision
12/2021 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Clackamas River Ranger District · updated 12/2/2021
Upper Clackamas Watershed · Clackamas; Marion, Oregon
This is an integrated resource management project in the Upper Clackamas Watershed that includes vegetation management, aquatic/riparian management and transportation system management.
Wildlife, fish, rare plantsForest productsVegetation management (other than forest products)Fuels managementRecreation managementRoad management
Comment Period
04/05/2017
Objection Period Start
11/03/2017
Decision
03/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | T.6 S., R.6 E.; T.6 S., R.7 E.; T.6 S., R.8 E.; T.7 S., R.7 E.; T.7 S., R.8 E.; T.8 S., R.7 E.; T.8 S., R.8 E.; T.9 S., R.7 E.; T.9 S., R.8 E.; Willamette Meridian. |
Environmental Assessment · Clackamas River Ranger District · updated 11/24/2021
Adjacent to roads 4220 and 4230 · Clackamas; Marion, Oregon
Construction of a shaded fuel break approximately 500 feet wide adjacent to Roads 4220 and 4230.
Fuels management
Comment Period
06/27/2010
Decision
09/2010 (Estimated)
Implementation
07/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Roadless Area Management; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | T7S,R8E,Sec 25,26,27,34,35,36; T7S, R8 1/2E, Sec 26,35; T8S, R8E, Sec 2,3,11,12,13,24,25,35,36, T9S, R8E, Sec 2 |
Decision Memo · Clackamas River Ranger District · updated 11/5/2021
Burned areas on the Clackamas River Ranger District · Clackamas; Jefferson; Marion, Oregon
The Clackamas District is proposing to repair recreation site facilities and structures and trail infrastructure that were destroyed or affected by the 2020 Riverside and Lionshead Fires.
Recreation management
Decision
11/2021 (Estimated)
Implementation
11/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 9/28/2021
Within the fire perimeters(2020 season)of the Clackamas River and Barlow Ranger Districts where moderate- to high-severity burning occurred and are at least two acres in size. · Clackamas; Marion; Wasco, Oregon
Reforest areas burned by the following fires that impacted the Mt. Hood National Forest during the summer of 2020: White River, Riverside, and Lionshead.
Vegetation management (other than forest products)
Decision
09/2021 (Estimated)
Implementation
09/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Zigzag Ranger District · updated 9/2/2021
In the Sandy and Salmon River watersheds. · Clackamas, Oregon
Stands have been identified that need thinning to enhance health and growth. Changes to the road system are included as well as riparian enhancements.
Fuels managementForest productsVegetation management (other than forest products)Wildlife, fish, rare plantsRoad managementRecreation management
Comment Period
07/11/2020
Objection Period Start
09/24/2020
Decision
09/2021 (Estimated)
Implementation
10/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 8/26/2021
Project activities will take place along two miles (19 acres) of the boundary of the Mt Hood National Forest and privately owned lands in the southeastern area of the Barlow Ranger District. · Wasco, Oregon
This project will fell and dispose of or remove fire killed and/or damaged trees that are along a two mile segment of the Mt. Hood National Forest boundary and private land.
Vegetation management (other than forest products)Forest productsFacility management
Decision
08/2021 (Estimated)
Implementation
09/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.5.S, R.11.E., Sections 17, 20. |
Decision Memo · Mt. Hood National Forest All Units · updated 8/25/2021
The White River West Sno Park is located on OR-35, northwest of the OR-35 and Forest Service Road 48 junction. · Hood River, Oregon
The purpose of this project is to maintain and repair the existing berm west of the White River to mitigate risks to Forest facilities including the White River West Sno-Park.
Recreation managementFacility management
Decision
08/2021 (Estimated)
Implementation
08/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Maintenance |
| Decision Decided Date | 08/25/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T 3S, R 9E, Section 16 |
Decision Memo · Barlow Ranger District · updated 8/19/2021
Clear Lake Campground · Wasco, Oregon
This project will install a gate on the road to Clear Lake Campground to facilitate enforcement of seasonal closures.
Facility management
Decision
08/2021 (Estimated)
Implementation
09/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 08/19/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.4.S., R.9.E., Section 32 |
Decision Memo · Clackamas River Ranger District · updated 8/17/2021
Adjacent to Forest roads and recreation sites in areas burned by the Riverside and Lionshead fires. · Clackamas, Oregon
Areas burned with the Riverside and Lionshead fires on the Clackamas River Ranger District.
Recreation managementFuels managementRoad managementForest products
Decision
08/2021 (Estimated)
Implementation
09/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3); 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Road Maintenance |
| Clackamas Fires Danger Tree Abatement Recreation and Administrative Sites | Decision Signed Date: 08/17/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 7/21/2021
Clear Branch Dam · Hood River, Oregon
This project will temporarily draw down Laurance Lake in order to conduct an investigative study of the Clear Branch Dam requiring drilling seven boreholes in the dam. During this time the area will be closed to the public.
ResearchFacility managementSpecial use management
Decision
07/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance; Research And Development |
| Decision Decided Date | 07/21/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T IS, R 9E, Sec. 27 NW NE , Willamette Meridian |
Decision Memo · Barlow Ranger District · updated 7/21/2021
Eightmile Day Use Area · Wasco, Oregon
This project will remove a tree-damaged toilet and install a new toilet in the same location at the Eightmile Day Use Area.
Recreation managementFacility management
Decision
07/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 07/21/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.2.S., R.10.E., section 8 |
Decision Memo · Mt. Hood National Forest All Units · updated 7/21/2021
Boulder Lake area · Wasco, Oregon
The purpose of the project is to remove two existing out-of-service cesspools and install up to two decomposting toilets at Boulder Lakes on the Barlow Ranger District.
Recreation managementFacility management
Decision
07/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 07/21/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.4.S., R.10.E., Section 5 |
Decision Memo · Hood River Ranger District · updated 6/30/2021
Lolo Pass (FS Road 1800-100); Frog Lake (FS Rd 2610); FS Road 4800 at OR-35. · Hood River, Oregon
This project will place gates in three locations in order to enforce seasonal road closures. At all locations gates will be professionally installed. Temporary road closures may be implemented during installation.
Facility managementRoad management
Decision
06/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Road Maintenance; Travel Management |
| Decision Decided Date | 06/30/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.2.S., R.8E, Section 2; T.4.S., R.9E, Section 17; T.3.S., R.9E, Section 16 |
Decision Memo · Barlow Ranger District · updated 6/14/2021
The area is bordered to the east by the forest boundary; to the west by Forest Roads 43 and 4330; to the north by Forest Roads 48 and 43; and to the south by Forest Roads 2110 and 2110250. · Clackamas, Oregon
The purpose of this project is to recover commercial value in dead and dying trees resulting from the White River Fire through offering them as forest products. The project would mechanically salvage trees on no more than 250 acres.
Forest products
Decision
06/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage) |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Township 4 South, Range 10 East, Section 34; Township 5 South, Range 10 East, Sections 1, 2, 12, and 14; and Township 5 South, Range 11 East, Section 5, 6, and 7. |
Decision Memo · Hood River Ranger District · updated 6/7/2021
T.2.S., R.9.E., section 15 · Hood River, Oregon
The purpose of the project is to replace the benches at the Tilly Jane Amphitheater site on the Hood River Ranger District. The existing benches have become dilapidated over time and are in need of repair.
Facility managementRecreation management
Decision
04/2021 (Estimated)
Implementation
05/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 04/07/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 6/4/2021
Outhouses would be installed at two locations: the Lost Lake Parking Lot and Barlow Pass Sno-Park parking area. · Hood River, Oregon
The purpose of this project is to install toilets (outhouses) at two locations on the Hood River Ranger District: the Lost Lake Parking Lot and Barlow Pass Sno-Park parking area.
Recreation managementFacility management
Decision
06/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Decision Decided Date | 06/04/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 4/5/2021
T.2.S., R.9.E., section 10 · Hood River, Oregon
This project will replace the roof and conduct minor rafter support repair for the Cloud Cap Inn.
Heritage resource managementRecreation managementFacility management
Decision
03/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Heritage Resource Management |
| Decision Decided Date | 03/31/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 3/5/2021
Tygh River Watershed. The legal description is: T03S, R11E, Section 24 and T03S, R12E, Sections 19, 20, 21, 28, 29, 30, 31, 32, and 33. · Wasco, Oregon
This project will reduce stand density and mitigate loss of trees from insect and disease-related mortality. The high density of trees, largely made up of dry, pine-oak habitat, has created a corridor where insect and disease can easily spread.
Vegetation management (other than forest products)Fuels management
Decision
03/2021 (Estimated)
Implementation
03/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| South Pen Insect and Disease Project Decision Memo | Decision Signed Date: 03/05/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Barlow Ranger District · updated 1/25/2021
The Dog River pipeline conveys water from the Dog River diversion dam to the south fork of Mill Creek. · Hood River; Wasco, Oregon
The existing Dog River pipeline, which is an important component of The Dalles' public drinking water supply, is deteriorating, leaking from tree damage, and exhibiting corrosion. This project proposes to replace the existing pipeline.
Special use management
Comment Period
11/10/2018
Objection Period Start
06/02/2020
Decision
10/2020 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T2S, R10E, Sections 2, 3, 4, 9, 10, and 11 |
Decision Memo · Hood River Ranger District · updated 11/6/2020
Clear Lake Butte, south of Clear Lake. · Wasco, Oregon
Remove failing shelter and replace it with a new prefabricated shelter; conduct road maintenance as needed to complete replacement of shelter.
Facility management
Decision
11/2020 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Road Maintenance |
| Decision Decided Date | 11/06/2020 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.4S.; R.9E.;section 7 |
Environmental Assessment · Barlow Ranger District · updated 10/21/2020
The CCR planning area is located at the southern end of both the Barlow and Hood River Ranger Districts, and includes parts of the White River and other watersheds in the Lower Deschutes sub-basin. · Hood River; Wasco, Oregon
The purpose of the Crystal Clear Restoration Project is to provide forest products where there is an opportunity to restore resiliency to forested areas and reduce the risk of uncharacteristic wildfire behavior.
Forest productsFuels management
Comment Period
08/25/2017
Objection Period Start
02/16/2018
Decision
06/2018 (Estimated)
Implementation
07/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.4S., R.8.5E.; T.4S., R.9E.; T.4S., R.10E.; T.5S., R.8.5E.; T.5S.,R.9.E.; T.5S., R.10E.; T.5S., R.11E.; Willamette Meridian |
Environmental Assessment · Hood River Ranger District · updated 9/30/2020
The planning area is on the Mt. Hood National Forest, Hood River Ranger District. This area is bordered by the Columbia River Gorge National Scenic Area, Mark O. Hatfield Wilderness, and private land. · Hood River, Oregon
This project proposes to improve huckleberry understory across the planning area to provide for functioning stand conditions over time that would favor long-term huckleberry production and growth.
Vegetation management (other than forest products)
Comment Period
02/18/2020
Objection Period Start
06/01/2020
Decision
09/2020 (Estimated)
Implementation
10/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Forest Vegetation Improvements; Species Habitat Improvements; Heritage Resource Management; Road Maintenance; Travel Management; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T 2 N, R 8 E, Sections 25 and 36;%uF0B7T 2 N, R 9 E, Section 16, 17, 19, 20, 21, and 28-33;%uF0B7T 1 N, R 8 E, Section 1, 2, 11, & 12; and T 1 N, R 9 E, Section 4. |
Environmental Assessment · Clackamas River Ranger District · updated 9/24/2020
Thinning and other vegetation management in the vicinity of Whale Head, Clackamas County, Oregon · Clackamas, Oregon
Vegetation management
Forest productsWildlife, fish, rare plantsVegetation management (other than forest products)Road management
Scoping Start
11/2020 (Estimated)
Comment Period
06/2021 (Estimated)
Objection Period Start
08/2021 (Estimated)
Decision
11/2021 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Mt. Hood National Forest All Units · updated 9/16/2020
Forestwide in Mt. Hood National Forest and Oregon sites in Scenic Area · Clackamas; Hood River; Jefferson; Marion; Multnomah; Wasco, Oregon
Prescribes treatments for invasive plants on Mt. Hood NF and Columbia River Gorge National Scenic Area in Oregon on approx. 13,000 acres (208 sites) with a combination of treatments including herbicide, manual, mechanical and cultural (goat grazing).
Vegetation management (other than forest products)
NOI in Federal Register
05/29/2005
DEIS NOA in Federal Register
05/26/2006
FEIS NOA in Federal Register
02/29/2008
Decision
02/2008 (Estimated)
Implementation
05/2008 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Noxious Weed Treatments |
| Site-Specific Invasive PLant Treatments for MHNF and CRGNSA in Oregon | Decision Signed Date: 02/29/2008 Legal Notice Date: 03/19/2008 |
| Forests | Mt. Hood National Forest; Columbia River Gorge National Scenic Area |
| Districts | Mt. Hood National Forest All Units; Columbia River Gorge National Scenic Area Unit |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 6/29/2020
Township 3 South, Range 8 East, sections 12, 13, and 24, and Township 3 South, Range 9 East, section 18 · Clackamas, Oregon
The proposed action would amend the Summit Ski Area special use permit to extend Summit's permit boundary northward to share a contiguous permit boundary with Timberline Lodge & Ski Area. No ground disturbance or vegetation removal is proposed.
Recreation management
Decision
06/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 6/24/2020
The project is located immediately adjacent to The Dalles Municipal Watershed within the Eightmile Watershed. · Wasco, Oregon
This project will reduce the risk of landscape level disturbance and increase forest resiliency to insect and disease. This project would reduce stand density on about 2,600 acres using mechanical and non-mechanical treatments.
Forest productsFuels management
Decision
06/2020 (Estimated)
Implementation
07/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T1S R11E Sections 15, 21-24, 26-29, & 31-33. T2S R11E Sections 5 & 6. |
Environmental Assessment · Hood River Ranger District · updated 6/16/2020
Laurance Lake is the reservoir constructed in 1968 by the installation of Clear Branch Dam. The project will impact the dam, reservoir, and pipes below the outlet. · Hood River, Oregon
This project looks to conduct dam-specific improvements as well as fisheries related improvements to support local anadromous fisheries.
Wildlife, fish, rare plantsSpecial use managementWatershed management
Comment Period
08/2018 (Estimated)
Objection Period Start
11/2018 (Estimated)
Decision
04/2019 (Estimated)
Implementation
06/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 6/12/2020
Projects are located within the permit areas of Mt. Hood Meadows Oreg. LLC, Teacup Lake Nordic Club, Cascadia Center for Arts and Crafts, and Mt. Hood Kiwanis Club. · Clackamas, Oregon
Ski run widening, waterline installation, conveyor system construction, building improvements, a dormitory building reconstruction, construction of four vault toilets, and the relocation of a shed.
Special use management
Decision
06/2020 (Estimated)
Implementation
07/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Special Uses Projects 2020: Waterline, Conveyors, Deck, Shed, Vault Toilets | Decision Signed Date: 06/12/2020 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District; Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 6/12/2020
Utilities projects are located within the permit area of Mt. Hood Meadows; one is in proximity to the Nordic Center parking lot, the other extends from the main parking area to the Mazot eatery. · Clackamas; Hood River, Oregon
At Mt. Hood Meadows: Install new fiber optic line through a parking lot to connect the Hood River Meadows Lodge and the Nordic Lodge, and to replace an existing power line that extends from the main parking lot to the Mazot eatery.
Special use management
Decision
06/2020 (Estimated)
Implementation
07/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Special Uses Projects 2020: Utilities at Mt. Hood Meadows Ski Area | Decision Signed Date: 06/12/2020 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 5/11/2020
Projects are proposed within the permit areas of Mt. Hood Meadows, Teacup Lake, and Ski Bowl all located on the Mt. Hood National Forest. · Clackamas; Hood River, Oregon
Consolidation of similar proposals: Construction of new hiking trails at Mt. Hood Meadows and new cross country ski trails at Teacup Lake; and at Ski Bowl, regrading the Alpine Easy Street trail and relocating a portion of another trail.
Special area management
Decision
07/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Clackamas River Ranger District · updated 1/31/2020
North Clackamas watershed. Roads 4610, 4611, 4612, 4613 and their tributaries. · Clackamas, Oregon
Vegetation management and other related projects in the North Clackamas area of the Clackamas River Ranger District.
Vegetation management (other than forest products)Fuels managementForest productsRecreation managementWildlife, fish, rare plantsRoad management
Comment Period
03/15/2019
Objection Period Start
08/17/2019
Decision
01/2020 (Estimated)
Implementation
03/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 12/10/2019
The proposed project would occur within the general area of Forest Roads 4410, 4420. · Hood River, Oregon
This proposal would reroute approximately 4 miles of the Cooks Meadow Trail and would establish better trail lay-out by removing the current route off a forest road.
Recreation management
Decision
09/2015 (Estimated)
Implementation
10/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Township 02 S., Range 10 E., Section 22, 27, 34, W.M. |
Environmental Assessment · Hood River Ranger District · updated 12/10/2019
West, East & Middle Fork of Hood River Subwatersheds · Hood River, Oregon
Improve forest health in West, East & Middle Fork of Hood River subwatersheds. Treatments include plantation thinning, firewood removal & huckleberry enhancement, plus decommissioning 2.1 miles and closing (year round & seasonal) 22.3 miles of roads.
Forest productsVegetation management (other than forest products)Watershed managementRoad management
Comment Period
12/04/2013
Objection Period Start
01/09/2015
Decision
04/2015 (Estimated)
Implementation
05/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Forest Vegetation Improvements; Special Products Sales; Noxious Weed Treatments; Road Maintenance; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Lava Restoration Final Decision Notice and Finding of No Significant Impact | Decision Signed Date: 04/29/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1S R8.5E Sections 25 and 36, T1S R9E Sections 1 and 6-36 |
Decision Memo · Barlow Ranger District · updated 12/10/2019
The Owl Underburn Project is located near Owl Hollow and along the 2730 and 2720 roads. · Wasco, Oregon
The Owl Undeburn Project would utilize prescribed fire to move the area towards historical fire regime and condition class. No temporary roads or harvest activities would occur as part of this project.
Wildlife, fish, rare plantsFuels management
Decision
11/2015 (Estimated)
Implementation
10/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Species Population Enhancements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Township 2S., Range 11 E., Sections 25,26,27,34,35,36. Township 3S., Range 11E., Sections 1,2 |
Decision Memo · Mt. Hood National Forest All Units · updated 12/6/2019
Mill Creek Buttes Repeater Site · Hood River, Oregon
Remove failing shelter and replace it with a new prefabricated shelter; conduct road maintenance as needed to complete replacement of shelter.
Road managementFacility management
Decision
12/2019 (Estimated)
Implementation
05/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3); 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Road Maintenance |
| Decision Decided Date | 12/06/2019 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T. 1 S., R. 10 E., section 34 |
Environmental Assessment · Zigzag Ranger District · updated 12/4/2019
The proposed project area is located on National Forest System Road (NFSR) 2600530, just north of US Highway 26 and Oregon Highway 173. · Clackamas, Oregon
The Mazamas are proposing to expand an existing 3-4 stall parking area located south of the Mazama Lodge on NFSR 2600530 into approximately 66 parking stalls and one bus pull-out, to mitigate a long-standing visitor safety issue.
Special use management
Comment Period
11/2016 (Estimated)
Objection Period Start
04/2016 (Estimated)
Decision
07/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T 3 S, R 8 1/2 E, Sec 24, WM. |
Decision Memo · Hood River Ranger District · updated 11/25/2019
Project activities will take place between the existing connection of the Laurence Lake waterline and the existing Coe Creek waterline, and the existing sediment basin. · Hood River, Oregon
Construct a waterline from Coe Creek to the Middle Fork Irrigation District (MFID) settling pond to improve water quality for the community served by MFID and reduce impacts of sedimentation on existing equipment operated by MFID and MFID customers.
Special use managementFacility management
Decision
11/2019 (Estimated)
Implementation
06/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Middle Fork Irrigation District Coe Water Pipeline Project | Decision Signed Date: 11/22/2019 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.1S.,R.9E.,S.27 |
Decision Memo · Mt. Hood National Forest All Units · updated 11/22/2019
The activities are proposed within the special use permit boundaries for Ski Bowl, Summit, and Mt. Hood Meadows ski areas. · Clackamas, Oregon
Proposals to develop a water containment system from defined spring sources for snow making, and construct a bus shelter at Ski Bowl; construct a temporary guest services structure at Summit Ski Area; and install night lighting at Mt. Hood Meadows.
Special use management
Decision
07/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 10/29/2019
Timberline Ski Area, on the Zigzag Ranger District of the Mt. Hood National Forest. · Clackamas, Oregon
This project proposes to replace the Pucci chairlift at the Timberline Ski Area.
Special use management
Decision
10/2019 (Estimated)
Implementation
06/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 10/21/2019
Along Forest Road 18 (Lolo Pass Road) and other Forest Roads east of Highway 35, on the Mt. Hood National Forest. · Clackamas; Hood River; Wasco, Oregon
The proposed project would authorize Zayo Group, LLC to construct, operate, and maintain approximately 14 miles of underground fiber optic conduit and cable and associated infrastructure along Forest Road 18 and other Forest roads east of Highway 35.
Special use management
Decision
10/2019 (Estimated)
Implementation
06/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District; Hood River Ranger District; Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 9/30/2019
Within the Bull Run Watershed Management Unit on the Mt. Hood National Forest. · Clackamas, Oregon
The Mt. Hood National Forest proposes to reissue the City of Portland's special use authorization for the operation, management and maintenance of the Bull Run Lake dam and reservoir for a new term of thirty years.
Special use management
Decision
09/2019 (Estimated)
Implementation
10/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Bull Run Lake Special Use Reauthorization | Decision Signed Date: 09/30/2019 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Mt. Hood National Forest All Units · updated 8/16/2019
Mt. Hood Wilderness · Clackamas; Hood River, Oregon
Four monitoring stations would be installed in Mt. Hood Wilderness. They would be assembled and maintained by U.S. Geological Survey. The data would assess volcanic activity and assist in communications regarding volcanic hazards and public safety.
ResearchSpecial use management
Comment Period
07/27/2016
Objection Period Start
03/15/2019
Decision
08/2019 (Estimated)
Implementation
09/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations; Research And Development |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District; Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 7/22/2019
Barlow Ranger District, along the National Forest System Road 44, from approximately Cook's Meadow to the Bottle Prairie area. · Hood River, Oregon
This project proposes to remove dead standing and live trees in two areas along National Forest System Road 44. Approximately 90 acres would be treated to increase area resiliency against large scale mortality events, while providing forest products.
Forest productsFuels management
Decision
07/2019 (Estimated)
Implementation
06/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (14), 36 Cfr 220.6(E)(14) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Products Sales; Timber Sales (Salvage) |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T02S R10E Sections 10, 11, 13, 14 |
Decision Memo · Mt. Hood National Forest All Units · updated 7/9/2019
Communication site projects are located at Mt. Hood Meadows, near Frog Lake at the AT&T site, and Forest Roads 29, 31, 35, and 35A/B. Fiber optic line installation is proposed along Forest Road 4631. · Clackamas; Hood River, Oregon
Replace existing communication towers at two locations: Mt. Hood Meadows and Frog Lake. There is also a proposal to install new fiber optic line along Forest Road (FR) 4631, and aerial fiber to residents along FRs 29, 31, 35, 35A and 35B.
Special use management
Decision
07/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Mt. Hood National Forest All Units · updated 6/11/2019
Tom, Dick and Harry Mt., Whale Head, Oak Grove Butte, Unnamed Hill Top · Clackamas, Oregon
Four radio towers would be installed to enhance emergency communications in Clackamas County.
Special use management
Comment Period
03/08/2019
Decision
05/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District; Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Barlow Ranger District · updated 5/8/2019
Rocky Restoration Project is located approximately 20 miles south of The Dalles, and just west of the community of Sportsman Park and the Rock Creek Reservoir. · Wasco, Oregon
The Rocky Restoration Project looks to improve the health and vigor of forested stands, and improve conditions for wildlife and aquatic resources, while reducing the risk of human-caused fires on nonfederal lands.
Vegetation management (other than forest products)Fuels managementForest productsWildlife, fish, rare plants
Comment Period
09/26/2018
Objection Period Start
12/14/2018
Decision
02/2019 (Estimated)
Implementation
05/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.03S R.10E Section 35,36, T.03S R.11E Section 35,36, T.03S R.12E Section 31, T.04S R.10E Section 1-3,10-15,T.04S R.11E Section 1-23, T.04S R.12E Section 6 |
Environmental Assessment · Zigzag Ranger District · updated 3/21/2019
Within the Bull Run Watershed Management Unit · Clackamas; Multnomah, Oregon
The Mt. Hood National Forest would convey 2,890 acres of land to the City of Portland, and acquire 2,200 acres of city land, all in the Bull Run Watershed Management Unit.
Land ownership managementWildlife, fish, rare plants
Comment Period
06/30/2017
Objection Period Start
09/05/2018
Decision
03/2019 (Estimated)
Implementation
05/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Land Exchanges |
| Bull Run Land Exchange Final DN/FONSI | Decision Signed Date: 03/20/2019 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 12/21/2018
Timberline Lodge · Clackamas, Oregon
The Forest Service has proposed to issue a permit to Verizon to install a Distributed Antenna System (DAS) inside of the historic Timberline Lodge and day lodge to improve cellular coverage inside the buildings.
Special use management
Decision
08/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T. 3S, R. 9E Sec 6 NE Corner |
Environmental Assessment · Mt. Hood National Forest All Units · updated 12/5/2018
PGE facilities on Clackamas, Hood River and Zigzag Ranger Districts. This project does not include facilities associated with Bethel-Round Butte Transmission Line or Clackamas Hydroelectric Project. · Clackamas; Hood River; Multnomah, Oregon
The primary purpose of this project is to renew and combine PGE's existing special use permits into one special use permit in order to allow PGE continued access, operation, and maintenance of existing powerline facilities.
Special use management
Comment Period
03/23/2018
Objection Period Start
07/14/2018
Decision
12/2018 (Estimated)
Implementation
12/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District; Hood River Ranger District; Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Mt. Hood National Forest All Units · updated 11/13/2018
Within the Mt. Hood Meadows Ski Resort Permit Area adjacent to the existing parking lot and attached to the existing South Lodge. · Hood River, Oregon
This project proposes to construct an addition to the South Lodge building at the Mt. Hood Meadows Ski Area.
Special use management
Comment Period
07/28/2018
Objection Period Start
09/21/2018
Decision
11/2018 (Estimated)
Implementation
03/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T3S, R9E, Section 4. |
Decision Memo · Mt. Hood National Forest All Units · updated 10/15/2018
Near Bennett Pass milepost 63 of Highway 35, on the Hood River Ranger District, Mt. Hood National Forest. · Hood River, Oregon
To reissue a special use authorization to ODOT for the management and operation of the sand shed and storage facility at the site, and authorize the construction of a fence that would define the perimeter of the site and minimize encroachment.
Special use management
Decision
10/2018 (Estimated)
Implementation
05/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 8/9/2018
Still Creek river mile 0.0 upstream to river mile 1.75. · Clackamas, Oregon
The proposed restoration includes improving stream function by adding large wood to the channel and floodplains, creating pools using boulder and log structures, opening up historic side channels, planting native plants, and removing invasive plants.
Wildlife, fish, rare plantsWatershed management
Decision
06/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Species Population Enhancements; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S, R7E, Sections 11 and 14 |
Environmental Assessment · Barlow Ranger District · updated 8/9/2018
The project area includes the White River watershed and Tygh Creek subwatershed. · Hood River; Wasco, Oregon
Decommissioning roads to improve hydrologic function and reduce adverse impacts to aquatic habitat on the Barlow and Hood River Ranger Districts
Wildlife, fish, rare plantsWatershed managementRoad management
Comment Period
10/2017 (Estimated)
Objection Period Start
02/2018 (Estimated)
Decision
04/2018 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District; Hood River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 5/21/2018
Across the Mt. Hood National Forest where instream and floodplain restoration needs are identified. · Clackamas; Hood River; Marion; Wasco, Oregon
The project proposes to complete aquatic restoration activities for instream and floodplain restoration across the forest.
Watershed management
Decision
05/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 5/17/2018
This amendment would apply across the Mt. Hood National Forest. · Clackamas; Hood River; Marion; Wasco, Oregon
To add the herbicide aminopyralid to the list of approved herbicides in the Forest Plan. This amendment is a relatively minor modification to the invasive plant program. It would not approve any projects on the ground.
Land management planningVegetation management (other than forest products)
Comment Period
03/30/2018
Decision
05/2018 (Estimated)
Implementation
07/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (16), 36 Cfr 220.6(E)(16) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Plan Amendment |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 5/17/2018
Across the Mt. Hood National Forest, where restoration needs are identified for aquatic organism passages and associated roads. · Clackamas; Hood River; Marion; Wasco, Oregon
The project proposes to complete aquatic restoration activities to improve or maintain aquatic organism passage across the forest.
Watershed management
Decision
05/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 5/17/2018
Where aquatic restoration is needed due to recreation-related impacts on the Mt. Hood National Forest. · Clackamas; Hood River; Marion; Wasco, Oregon
The project proposes to complete recreation-related restoration to improve stream and aquatic function across the forest.
Watershed management
Decision
05/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 3/22/2018
Within the boundary of the Mt. Hood National Forest and potentially adjacent lands where restoration activities would achieve agency aquatic restoration goals. · Clackamas; Hood River; Marion; Wasco, Oregon
The project proposes to complete an aquatic restoration programmatic in order to achieve specific aquatic restoration activities across the forest.
Watershed management
Decision
04/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3); 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (9), 36 Cfr 220.6(E)(9); 32.2 (12), 36 Cfr 220.6(E)(12); 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Barlow Ranger District · updated 3/15/2018
T01S R10E and R11E, T02S R10E R11E, and R12E, and T03S R10E, R11E, and R12E. Willamette Meridian · Wasco, Oregon
The Barlow Ranger District proposes to mechanically thin, masticate, pile, and brush sapling plantations approximately 3,800 acres. The project consists of small diameter thinning (0-8" DBH) on slopes less than 40 percent.
Vegetation management (other than forest products)Fuels managementWildlife, fish, rare plants
Decision
03/2018 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Hood River Ranger District · updated 11/30/2017
East Fork Hood River Watershed; Pinnacle Creek, East and Middle Fork of the Hood River, and Dog River Subwatersheds · Hood River, Oregon
Reduce fuels loading in fire adapted plant communities in the Cooper Spur Wildland Urban Interface located in the East Fork of Hood River watershed. Treatments may include plantation thinning, firewood removal, fuel break & natural stand thinning.
Forest productsFuels management
Comment Period
01/26/2016
Objection Period Start
08/31/2017
Decision
11/2017 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 (2013) HFRA |
| Project Activity | Biomass; Fuel Treatments (Non-Activity Fuels); Timber Sales (Salvage); Timber Sales (Green) |
| Polallie Cooper Hazardous Fuels Reduction - Phase 1 | Decision Signed Date: 11/30/2017 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1S, R9E Sections 10-11, 14-15, 35-39, PB43 & PB44; T1S R10E Sections 4-10, 17-18 & 32-33 |
Environmental Assessment · Clackamas River Ranger District · updated 9/30/2017
Indian Henry Campground · Clackamas, Oregon
Assessment of options to deal with removing hazard trees caused by root diseases in Indian Henry Campground and modernization of facilities. Most of campground is closed at this time due to hazard.
Facility managementRecreation management
Comment Period
07/2015 (Estimated)
Objection Period Start
11/2015 (Estimated)
Decision
03/2016 (Estimated)
Implementation
03/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 9/25/2017
Township 2 South, Range 9 East, Section 7. · Clackamas, Oregon
This project proposes to install two vault toilets near Phlox Point Cabin, which is within the Timberline Lodge Resort and Ski Area permit area. The existing portable facilities would be removed.
Special use management
Decision
09/2017 (Estimated)
Implementation
10/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 8/14/2017
T. 3 S., R. 8 E., Section 24 NW 1/4. · Clackamas, Oregon
This project analyzes the Government Camp Sanitation District's proposal to construct and install a new surge tank at their treatment facility.
Special use management
Decision
08/2017 (Estimated)
Implementation
08/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Government Camp Sanitary District Surge Tank | Decision Signed Date: 08/10/2017 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 7/18/2017
This project is located on the Zigzag Ranger District, at T. 3 S., R. 7 E., Sec. 11. The project area is accessible by Henry Creek Road off of Highway 26. · Clackamas, Oregon
This project analyzes Rhododendron Water Association's special uses project proposal to construct and install a new sand water filtration at their water treatment facility.
Special use management
Decision
06/2017 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T. 3 S., R. 7 E., Sec. 11. |
Decision Memo · Mt. Hood National Forest All Units · updated 3/15/2017
Mt. Hood National Forest, Clackamas River, Zigzag and Hood River Ranger Districts within existing utility corridors and/or road rights-of-way. · Clackamas; Hood River, Oregon
This project analyzes a combination of proposals from Cascade Utilities for installing new fiber optic line within road rights of way and existing utility corridors.
Special use management
Decision
03/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District; Hood River Ranger District; Zigzag Ranger District |
| Legal Land Description | T3SR8.5ESec.24 and 25 and T3SR9ESec. 30 and 31. T4SR9ESec. 6, 7, 8, 17, and 20. T3SR9E Sec. 3. T5S, R6E, Sec. 34, and T6S, R6E, Sec. 3, and T6S, R6E, Sec. 2. T6S, R6E, Sec. 2. |
Decision Memo · Zigzag Ranger District · updated 10/26/2016
The project area is located on the graveled portions of Road 2656 and some of its spur roads. · Clackamas, Oregon
The Zigzag fisheries staff propose to remove approximately 700 to 1,000 whole trees for use in stream and floodplain restoration projects in the Sandy River Basin over the next 5-10 years.
Wildlife, fish, rare plantsWatershed management
Decision
10/2016 (Estimated)
Implementation
04/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 9/29/2016
Surveyor's Ridge Trail #668 · Hood River, Oregon
The Surveyor's Ridge Trail would be re-routed where it will be impacted by the City of the Dalles pipeline replacement. Additional trailhead parking will also be created.
Recreation management
Decision
07/2016 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T2S, R10E Sec 3 and 10 |
Decision Memo · Mt. Hood National Forest All Units · updated 6/29/2016
West Fork of Hood River- the Red Hill area · Hood River, Oregon
The West Fork Hood River Restoration project would restore habitat for listed fish species by restoring the stream and stream function by adding large wood debris to the stream.
Wildlife, fish, rare plants
Decision
06/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1S R8E Sec 13NE |
Decision Memo · Zigzag Ranger District · updated 6/3/2016
Within the top terminal building of the Mile Chair Lift at the Timberline Ski Area · Clackamas, Oregon
The project proposes to authorize RLK & Company use at the top terminal of the Mile Chair Lift as a communication facility within the existing operating guidelines of the Timberline Communication Site Plan.
Special use management
Decision
04/2016 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S, R9E, SW corner of section 13 and NW corner of section 6 |
Decision Memo · Zigzag Ranger District · updated 6/3/2016
Skibowl Ski Area · Clackamas, Oregon
Antiquated technology and dynamic environmental conditions have created the need to regularly improve snowmaking infrastructure. Therefore, this project would expand and upgrade the existing snowmaking infrastructure in the Skibowl Ski Area.
Recreation managementSpecial use management
Decision
05/2016 (Estimated)
Implementation
08/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 5/11/2016
Summit compound buildings and the lower a frame and the upper a frame at the intersection of Timberline Rd and HWY 26. · Clackamas, Oregon
The purpose of this project is to re-issue a 10 year special use permit authorization for the Cascadia Center for the Arts to utilize Government owned facilities for the purposes of the Cascadian Arts program in Government Camp, Oregon.
Special area management
Decision
05/2016 (Estimated)
Implementation
05/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Area Management |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S R8E Sec 24 and 33 |
Decision Memo · Mt. Hood National Forest All Units · updated 4/29/2016
Sisi Butte · Clackamas, Oregon
Renewal of the Special Use Permit for the Verizon Communication Site at Sisi Butte. The only change will be allowing the permit holder to use FSR 4220120, which is approximately 2 miles.
Special use management
Decision
04/2016 (Estimated)
Implementation
05/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Clackamas River Ranger District · updated 2/26/2016
Lemiti Butte · Clackamas; Marion, Oregon
Fuels reduction and salvage of bug killed lodgepole pine on approximately 1,400 acres. Fuel treatments would include a mix of actions such as harvesting and removing trees, precommercial thinning, pruning, slash piling and pile burning.
Forest productsFuels management
Comment Period
08/07/2015
Objection Period Start
09/16/2015
Decision
02/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Salvage) |
| Lemiti Fuels Reduction Project and Forest Plan Amendment #19 | Decision Signed Date: 02/26/2016 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 2/16/2016
Near Estacada · Clackamas, Oregon
Native Vegetation Planting and Danger Tree Removal Project in 36 Pit Fire Burned Area
Recreation managementVegetation management (other than forest products)Road management
Decision
02/2016 (Estimated)
Implementation
03/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (11), 36 Cfr 220.6(E)(11) |
| Special Authority | National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Trail Management; Road Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | T. 4 S., R. 5 E |
Decision Memo · Hood River Ranger District · updated 1/12/2016
The reconstruction would occur approximately 1 mile north of the former Timberline Trail crossing of Eliot Branch · Hood River, Oregon
A debris flow in 2006 washed out this portion of the Timberline Trail creating a barrier to circumnavigate Mt. Hood. The proposal would reconstruct approximately 1.5 miles of the Timberline Trail across Eliot Branch.
Recreation management
Decision
01/2016 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T 02S., R 9E., Section 10,15 |
Environmental Assessment · Clackamas River Ranger District · updated 11/10/2015
district wide · Clackamas; Marion, Oregon
Formerly called Restoration 2014. Fish habitat, watershed restoration, & water quality restoration projects. Projects include instream log & boulder placement, side channel creation, road closure, decommissioning & repair of vehicle damage.
Wildlife, fish, rare plantsWatershed management
Comment Period
04/25/2014
Objection Period Start
09/09/2015
Decision
11/2015 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Watershed Improvements |
| 2015 Clackamas Restoration Projects | Decision Signed Date: 11/09/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 9/21/2015
The proposed replacement powerline is near the Summit Ski Area. · Clackamas, Oregon
In order to provide safe and reliable power, PGE has proposed to replace a current buried powerline that is failing due to aging. This new line (about 1,300 feet in length) will be installed adjacent to the existing line, which will remain in ground.
Special use management
Decision
09/2015 (Estimated)
Implementation
09/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S R8E Section SW13 and NW24 |
Decision Memo · Mt. Hood National Forest All Units · updated 9/15/2015
Northwest of the Mt. Hood Meadows Ski Area's administration building · Hood River, Oregon
Because of low voltage problems caused by above ground regulators, PGE has proposed to replace the existing pole mounted regulator with a more reliable, in-ground vault.
Special use management
Decision
09/2015 (Estimated)
Implementation
09/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Memo | Decision Signed Date: 09/04/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T3S, R9E, Section 4 SE SE |
Environmental Assessment · Clackamas River Ranger District · updated 9/11/2015
Oak Grove and Middle Clackamas Watershed · Clackamas, Oregon
Thinning of second-growth stands in the Oak Grove and Middle Clackamas Watersheds
Forest products
Comment Period
02/28/2014
Decision
10/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Timber Sales (Green) |
| Grove Thinning | Decision Signed Date: 10/20/2014 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Hood River Ranger District · updated 9/11/2015
Mt. Hood Meadows Ski Resort · Hood River, Oregon
This project builds the Twilight Parking Lot to expand parking and constructs a new, upgraded maintenance shop. All alternatives include installing utilities lines, building access roads, constructing turn lanes, and constructing Nordic ski trails.
Special use managementRecreation management
NOI in Federal Register
07/08/2011
DEIS NOA in Federal Register
05/03/2013
FEIS NOA in Federal Register
01/17/2014
Objection Period Start
01/17/2014
Decision
06/2014 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Special Use Authorizations; Trail Management; Road Improvements/Construction |
| Mt. Hood Meadows Parking Improvements ROD | Decision Signed Date: 06/11/2014 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Sections 10 & 11, T3S, R 9E |
Environmental Assessment · Hood River Ranger District · updated 9/11/2015
The planning area includes North Fork of Mill Creek watershed and small portions of Mosier and Neal Creek watersheds. It is located approximately 5 miles east of the town of Mt. Hood. · Hood River; Wasco, Oregon
Analyze changed conditions resulting from the Government Flats fire and assess how this impacts existing contractual obligations on two stewardship sales. The proposed treatments include restoration thinning, hazard tree treatments and reforestation.
Road managementFuels managementForest productsVegetation management (other than forest products)
Comment Period
06/18/2014
Decision
01/2015 (Estimated)
Implementation
04/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Salvage); Timber Sales (Green) |
| North Fork Mill Creek Revised Decision Notice | Decision Signed Date: 01/16/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District; Hood River Ranger District |
| Legal Land Description | T1S, R11E, Sections 4-9 |
Environmental Assessment · Zigzag Ranger District · updated 6/27/2015
The majority of project activities would occur in the Upper Sandy River and Zigzag River watersheds. · Clackamas, Oregon
Decommissioning roads to improve hydrologic function and reduce adverse impacts to aquatic and terrestrial habitats on the Zigzag Ranger District.
Wildlife, fish, rare plantsWatershed managementRoad management
Comment Period
09/21/2009
Decision
04/2010 (Estimated)
Implementation
06/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning |
| Zigzag Road Decommissioning for Habitat Restoration, Increment 2 | Decision Signed Date: 04/05/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
Decision Memo · Zigzag Ranger District · updated 6/22/2015
The Pioneer Bridle trail is located between Glacier View Snopark and Tollgate Trailhead. · Clackamas, Oregon
The Pioneer Bridle trail will need to be relocated and reconstructed in sections where the ODOT highway expansion project will effect the trail location. Aproximately 1/2 mile of trail over a 2-mile stretch will be relocated.
Recreation management
Decision
06/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Reconstruction of Pioneer Bridle Trail #795 | Decision Signed Date: 06/04/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Mt. Hood National Forest All Units · updated 6/22/2015
The bridge is located on the Pacific Crest Trail where the trail crosses the Muddy Fork River. The easiest way to access the trail bridge is by Ramona Falls Trailhead. · Clackamas, Oregon
Portions of the Sandy River Trail would be reconstructed by installing drainage structures including drain dips, waterbars, rock armoring and check dams.
Recreation management
Decision
06/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Reconstruction of the Sandy River Trail #770 | Decision Signed Date: 06/04/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 6/9/2015
Water line serves the recreation residents along National Forest Service Roads 2620, 220E, and 2632. · Clackamas, Oregon
Replace and upgrade existing Lady Creek waterlines serving recreation residence cabins because the existing lines are leaking and have reached the end of their service life. These waterlines are along National Forest System Roads 2620, 220E and 2632.
Special use management
Decision
06/2015 (Estimated)
Implementation
07/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lady Creek Waterline Replacement | Decision Signed Date: 06/03/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S, R7E, Section 11 and T3S, R8E, Section 32 |
Decision Memo · Hood River Ranger District · updated 5/18/2015
The proposed project would occur on 34 acres within and around the Tilly Jane Campground located on the Hood River Ranger District of the Mt. Hood National Forest. · Hood River, Oregon
The purpose of the project is to remove ladder fuel on 34 acres within and around the Tilly Jane Campground to protect the historic site and campground from a large scale disturbance.
Heritage resource managementRecreation managementFuels management
Decision
05/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Decision Memo for Tilly Jane Hazardous Fuels Reduction Project | Decision Signed Date: 05/11/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | Township 02 S., Range 09 E., Section 14, 15. Willamette Meridian |
Decision Memo · Mt. Hood National Forest All Units · updated 5/7/2015
Bull Run Watershed Management Unit · Clackamas, Oregon
Change all Land Use Allocations to DA-1 (Bull Run Watershed)and DA-3 (Research Natural Area) and update the Plan Standards & Guidlines to comply with Omnibus Parks & Public Lands Management and Little Sandy River Watershed Protection Acts.
Land management planning
Scoping Start
04/2015 (Estimated)
Comment Period
04/2015 (Estimated)
Objection Period Start
06/2015 (Estimated)
Decision
08/2015 (Estimated)
Implementation
08/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (16), 36 Cfr 220.6(E)(16) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Plan Amendment |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Zigzag Ranger District · updated 3/16/2015
1,300 feet from Tyrolean Drive west to the Government Camp Sewage Treatment Plant. The first 500 feet will be in the south shoulder of US Highway 26 and then cross Skibowl west parking lot. · Clackamas, Oregon
Clackamas County is proposing to bury a 12-inch diameter waterline in Government Camp, approximately 1,300 feet from Tyrolean Drive west to the access road for the Government Camp Sewage Treatment Plant, and for a fire hydrant at Skibowl West.
Special use management
Decision
03/2015 (Estimated)
Implementation
03/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Clackamas County Waterline Extension at Government Camp | Decision Signed Date: 03/10/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T 3 S, R 8 E, Sec 24, WM |
Environmental Assessment · Clackamas River Ranger District · updated 4/22/2014
Collawash Watershed · Clackamas, Oregon
The purpose of this project is to thin second-growth plantations to achieve multiple objectives. Thinning would occur in matrix, late-successional reserves and riparian reserves.
Wildlife, fish, rare plantsForest products
Comment Period
11/18/2011
Decision
03/2013 (Estimated)
Implementation
09/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
Environmental Assessment · Zigzag Ranger District · updated 12/20/2013
The project is located on the Zigzag Ranger District near Government Camp, Oregon. · Clackamas, Oregon
Improve public agency emergency service communications available along the highways leading to Mt. Hood and the Timberline Ski Area, as well as the surrounding forestlands.
Special use management
Comment Period
07/13/2013
Decision
10/2013 (Estimated)
Implementation
11/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| C800 Group Communication Facility DN and FONSI | Decision Signed Date: 10/21/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S, R8E, Section 6 |
Decision Memo · Clackamas River Ranger District · updated 12/9/2013
Near Ripplebrook and Lake Harriet · Clackamas, Oregon
Installation of sirens on poles to warn forest visitors in the event of a dam failure.
Special use management
Comment Period
08/05/2013
Decision
11/2013 (Estimated)
Implementation
12/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| PGE Siren Installation | Decision Signed Date: 11/15/2013 Legal Notice Date: 11/15/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Section 2 of T.6 S., R.6 E.; and Section 4 of T.7 S., R.6 E.; WM |
Decision Memo · Hood River Ranger District · updated 10/22/2013
Coe Branch Adjacent to the Middle Fork Irrigation District Coe Branch Irrigation Diversion · Wasco, Oregon
Middle Fork Irrigation District proposes to construct a roughened channel at two existing partial fish passage barriers. Large boulders would be added to the channel below the existing boulder weirs to create a steep riffle that is passable by fish.
Special use managementWildlife, fish, rare plants
Comment Period
08/29/2013
Decision
10/2013 (Estimated)
Implementation
10/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Special Use Authorizations; Watershed Improvements |
| Middle Fork Irrigation District Coe Branch Diversion Grade Control Project | Decision Signed Date: 10/01/2013 Legal Notice Date: 10/22/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T1S, R9E, Section 27 |
Decision Memo · Zigzag Ranger District · updated 9/30/2013
Skibowl West Ski Resort · Clackamas, Oregon
Construction of an electric vehicle charging station in the Skibowl West parking lot
Special use management
Comment Period
05/30/2013
Decision
07/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Electric Vehicle charging Station at Skibowl West | Decision Signed Date: 07/11/2013 |
| Electic Vehicle Charging Station at Skibowl West | Decision Signed Date: 07/11/2013 Legal Notice Date: 07/18/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
Environmental Assessment · Hood River Ranger District · updated 9/19/2013
Mt. Hood Meadows Ski Resort · Hood River, Oregon
To increase capacity and improve traffic flow, a new ski lift and new terminal sites will be installed and the alignment will be changed and extended at Buttercup ski lift. A new access road and utility lines will be constructed as connected actions.
Recreation managementSpecial use management
Comment Period
07/19/2013
Decision
09/2013 (Estimated)
Implementation
05/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T3S, R9E, Section 4 |
Decision Memo · Barlow Ranger District · updated 8/19/2013
Rock Creek Designated OHV Location (Forest Service Road 4830) · Wasco, Oregon
Construct a trail from Gate Creek Staging Area to Forest Service Road 4830. The trail would be would have two stream crossings over Gate Creek. This would add 0.8 miles of newly designated OHV trail and 0.2 miles of new mixed-use along FSR 4830.
Recreation management
Comment Period
05/28/2013
Decision
08/2013 (Estimated)
Implementation
05/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management; Travel Management |
| Gate Creek OHV Crossing | Decision Signed Date: 08/14/2013 Legal Notice Date: 08/16/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T4S, R11E, Section 26 |
Decision Memo · Mt. Hood National Forest All Units · updated 8/1/2013
Henry Creek near Rhododendron, OR · Clackamas, Oregon
Structural reinforcement to the exposed underside of the diversion structure for the Rhododendron Water Association's operations in Henry Creek, which has eroded away and is in need of repair.
Special use management
Comment Period
06/20/2013
Decision
07/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Rhododendron Water Association Diversion Dam and Fish Screen Improvement | Decision Signed Date: 07/23/2013 Legal Notice Date: 07/31/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T 3S, R 7E, Sec. 11 & 12 |
Environmental Impact Statement · Mt. Hood National Forest All Units · updated 6/21/2013
Boardman, Oregon to Pine Grove, Oregon · Wasco, Oregon
Portland General Electric proposes to construct, maintain, and operate a 500 kV, single-circuit transmission line that would cross 1.2 miles of the Mt. Hood National Forest.
Special use management
NOI in Federal Register
06/01/2010
DEIS NOA in Federal Register
10/2013 (Estimated)
FEIS NOA in Federal Register
05/2014 (Estimated)
Decision
10/2014 (Estimated)
Implementation
03/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Electric Transmission |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
Decision Memo · Hood River Ranger District · updated 6/17/2013
Laurenace Lake and Settling Pond approximately seven miles SW of Parkdale, Oregon · Hood River, Oregon
Middle Fork Irrigation District will complete four miantenence projects within their permit area: (1) Clear Branch Dam Parapet Wall Refurbishment; (2) Right-of-Way Bushing; (3) Sediment Basin Cleaning; and, (4) Wood Placement Below Clear Branch Dam.
Special use management
Comment Period
02/19/2013
Decision
06/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Hydropower; Facility Maintenance |
| Middle Fork Irrigation District 2013 Maintenance Projects | Decision Signed Date: 06/06/2013 Legal Notice Date: 06/12/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1S, R9E, Sections 23, 26, 27, and 28 |
Decision Memo · Barlow Ranger District · updated 6/6/2013
City of The Dalles Municipal Watershed (Forest Service Roads 1700 and 1720) · Wasco, Oregon
Construct 4 miles of trail to move existing route off FS Roads 1700 & 1720. Minimal clearing would be needed since the majority of the project is on skid roads used for The Dalles Fuelbreak project. Only 0.4 miles of trail would be new construction.
Recreation management
Comment Period
04/03/2013
Decision
06/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T1S and T2S, R10E, Sections 1, 2, 3 and 34 |
Environmental Assessment · Hood River Ranger District · updated 6/3/2013
Upper West Fork Hood River Subwatershed (Red Hill Area) · Hood River, Oregon
Improve forest health in Upper West Fork Hood River subwatershed. Treatments include plantation thinning, riparian enhancement, fuels reduction, habitat improvement & huckleberry enhancement. Treatments will occur on 1,500 acres in the Red Hill area.
Watershed managementForest products
Comment Period
11/17/2012
Decision
05/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Red Hill Restoration Decision Notice and Finding of No Significant Impact | Decision Signed Date: 05/29/2013 Legal Notice Date: 06/01/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1S R8-9E; T2S, R8E |
Decision Memo · Hood River Ranger District · updated 5/16/2013
Mt. Hood Meadows Ski Resort Permit Area · Hood River, Oregon
Complete maintenance projects within Mt. Hood Meadows Ski Resort permit area. Projects include: trail sign replacement, new trail signs at Shooting Star, Nordic ski trail maintenance, Kinnikinnick stumping grinding, and fiber optic line installation.
Special use managementRecreation management
Comment Period
03/06/2013
Decision
05/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Trail Management |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T3S, R9E, Section 4 |
Decision Memo · Zigzag Ranger District · updated 4/26/2013
Still Creek, Salmon River, Hood River, Fifteenmile, and Clackamas River watersheds. · Clackamas; Hood River; Wasco, Oregon
Restore specific high priority watersheds that have been identified through Watershed Restoration Action Plans as well as other high priority restoration projects outside these watersheds.
Watershed managementWildlife, fish, rare plantsRoad management
Comment Period
03/15/2013
Decision
04/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Dispersed Recreation Mgmt.; Species Habitat Improvements; Species Population Enhancements; Road Maintenance; Watershed Improvements |
| Forestwide Restoration Decision Memos (3) | Decision Signed Date: 04/23/2013 Legal Notice Date: 04/26/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
Decision Memo · Mt. Hood National Forest All Units · updated 3/22/2013
Along the proposed route and alternatives on the Mt. Hood and Willamette National Forests. · Clackamas; Marion, Oregon
Geotechnical investigations on National Forest System lands for the proposed Cascade Crossing Transmission Project
Minerals and geology
Decision
11/2012 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest; Willamette National Forest |
| Districts | Clackamas River Ranger District; Detroit Ranger District |
Environmental Assessment · Zigzag Ranger District · updated 11/27/2012
Timberline Ski Area, Mt. Hood, Oregon · Clackamas, Oregon
RLK & Company propose to develop a managed, lift-assisted mountain bike trails and skills park within the permit area of the Timberline Ski Area. Approximately 8-9 acres of ground disturbance would occur.
Recreation management
Comment Period
03/05/2011
Decision
11/2012 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Trail Management |
| Timberline Ski Area Mountain Bike Trails and Skills Park | Decision Signed Date: 11/19/2012 Legal Notice Date: 11/27/2012 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S, R9E, sections 7, 12, and 13 |
Decision Memo · Mt. Hood National Forest All Units · updated 10/29/2012
Forest Wide · Clackamas, Oregon
bough harvest across the forest
Forest products
Comment Period
07/23/2012
Decision
10/2012 (Estimated)
Implementation
09/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Products Sales |
| Forest-Wide Bought Program | Decision Signed Date: 10/22/2012 |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
Decision Memo · Barlow Ranger District · updated 10/11/2012
The project is in close proximity to the community of Sportsman's Park and may also include underburning on Oregon Department of Fish and Wildlife managed land. · Wasco, Oregon
Hand-thin and underburn approximately 1,215 acres of ponderosa pine/Oregon white oak and ponderosa pine/Douglas-fir stands. Only trees less than 8-inch diameter at breast height (DBH) would be removed.
Vegetation management (other than forest products)Fuels management
Comment Period
05/07/2012
Decision
07/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T4S RIlE Sections 10, 13, 14, 15,23 and 24 |
Decision Memo · Clackamas River Ranger District · updated 9/6/2012
Lemiti · Clackamas, Oregon
Installation of a device to provide drinking water to wildlife
Wildlife, fish, rare plants
Comment Period
04/28/2012
Decision
06/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
Decision Memo · Hood River Ranger District · updated 8/30/2012
Meadows Creek lies within the boundaries of the Mt. Hood National Forest and is a tributary to the East Fork Hood River · Hood River, Oregon
Replace two culverts on Meadows Creek to remove fish passage barriers. The culverts are located: under Highway 35 (at approximately river mile (RM) 1.8) and the one immediately downstream of the Highway (on Forest Road 3500-680).
Wildlife, fish, rare plantsRoad management
Comment Period
07/09/2012
Decision
08/2012 (Estimated)
Implementation
05/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Species Population Enhancements; Watershed Improvements |
| Culvert Replacement on Meadows Creek at Highway 35 &Forest Road 3500-680 | Decision Signed Date: 08/28/2012 Legal Notice Date: 08/30/2012 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T3S, R9E, Sections 11 and 12 |
Decision Memo · Zigzag Ranger District · updated 8/16/2012
Wildcat Mtn. Road at the eastern Forest boundary; Hunchback Mtn. to the south of Hwy 26 at Zig Zag; Lower Drift Creek 4 mi east of Waldport, OR · Clackamas; Lincoln, Oregon
The Forest Service would convey 160 acres of property on Wildcat Mtn. Road and acquire 160 acres of county land at Hunchback Mountain near Zigzag, Oregon, and aqcuire 276 acres of land near Waldport, Oregon.
Land ownership management
Decision
05/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Exchanges |
| Forests | Mt. Hood National Forest; Siuslaw National Forest |
| Districts | Zigzag Ranger District; Central Coast Ranger District/Oregon Dunes National Recreation Area |
Decision Memo · Zigzag Ranger District · updated 8/2/2012
North from the road in front of Timberline Lodge to the PCT and up to Silcox. If funds exist, west to the amphitheater and east to the water tower. · Clackamas, Oregon
This project will relocate short sections of trail and reconstruct the walking trails above Timberline Lodge to the PCT. It will remove the broken asphalt and replace the trails with packed gravel. At least one trail will be ADA compliant.
Recreation management
Comment Period
04/28/2012
Comment Period
04/28/2012
Decision
07/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| 2012 Timberline Pedestrian Trail Enhancement Project | Decision Signed Date: 07/17/2012 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
Environmental Impact Statement · WO - Washington Office - National headquarters · updated 7/10/2012
11 contiguous Western States (Arizona, California, Colorado, Idaho, Montana, New Mexico, Nevada, Oregon, Utah, Washington, and Wyoming) and Alaska. · Bonner; Aleutians East; La Paz; Columbia; Coos; Colusa; Denver; Douglas, Alaska; Arizona; California; Colorado; District of Columbia; Idaho; Kansas; Montana; North Dakota; Nebraska; New Mexico; Nevada; Oklahoma; Oregon; South Dakota; Texas; Utah; Washington; Wyoming
The Forest Service was a cooperating agency, assisting the Bureau of Land Management (BLM) in that Agency's geothermal leasing analysis and decision. The BLM issued a record of decision on 12/17/2008.
Regulations, directives, orders
NOI in Federal Register
06/13/2007
DEIS NOA in Federal Register
06/13/2008
FEIS NOA in Federal Register
10/24/2008
Decision
02/2010 (Estimated)
Implementation
03/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Regulation Creation/Modification |
| Forests | Beaverhead-Deerlodge National Forest; Bitterroot National Forest; Clearwater National Forest; Custer National Forest; Custer Gallatin National Forest; Helena National Forest; Lewis And Clark National Forest; Lolo National Forest; Nez Perce-Clearwater National Forest; Grand Mesa, Uncompahgre and Gunnison National Forests; Medicine Bow-Routt National Forest; Rio Grande National Forest; Arapaho and Roosevelt National Forests; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands; San Juan National Forest; White River National Forest; Apache-Sitgreaves National Forests; Carson National Forest; Cibola National Forest; Coronado National Forest; Gila National Forest; Lincoln National Forest; Santa Fe National Forest; Tonto National Forest; Boise National Forest; Bridger-Teton National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Payette National Forest; Salmon-Challis National Forest; Sawtooth National Forest; Caribou-Targhee National Forest; Humboldt-Toiyabe National Forest; Uinta-Wasatch-Cache National Forest; Angeles National Forest; Cleveland National Forest; Eldorado National Forest; Inyo National Forest; Klamath National Forest; Lassen National Forest; Los Padres National Forest; Mendocino National Forest; Modoc National Forest; Plumas National Forest; San Bernardino National Forest; Sequoia National Forest; Shasta Trinity National Forest; Sierra National Forest; Tahoe National Forest; Deschutes National Forest; Fremont-Winema National Forest; Gifford Pinchot National Forest; Malheur National Forest; Mt Baker-Snoqualmie National Forest; Mt. Hood National Forest; Ochoco National Forest; Rogue River-Siskiyou National Forest; Umatilla National Forest; Umpqua National Forest; Wallowa-Whitman National Forest; Okanogan-Wenatchee National Forest; Willamette National Forest; R10 - Alaska Region All Units; WO - Washington Office - National headquarters |
| Districts | Beaverhead-Deerlodge National Forest All Units; Bitterroot National Forest All Units; Clearwater National Forest All Units; Custer National Forest All Units; Custer Gallatin National Forest; Custer Gallatin National Forest All Units; Helena National Forest All Units; Lewis And Clark National Forest All Units; Lolo National Forest All Units; Nez Perce-Clearwater National Forest All Units; Grand Mesa Uncompahgre and Gunnison National Forest All Units; Medicine Bow-Routt National Forest All Units; Rio Grande National Forest All Units; Arapaho and Roosevelt National Forests All Units; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands All Units; San Juan National Forest All Units; White River National Forest All Units; Apache-Sitgreaves National Forests All Units; Carson National Forest All Units; Cibola National Forest All Units; Coronado National Forest All Units; Gila National Forest All Units; Lincoln National Forest All Units; Santa Fe National Forest All Units; Tonto National Forest All Units; Boise National Forest All Units; Bridger-Teton National Forest All Units; Dixie National Forest All Units; Fishlake National Forest All Units; Manti-La Sal National Forest All Units; Payette National Forest All Units; Salmon-Challis National Forest All Units; Sawtooth National Forest All Units; Caribou-Targhee National Forest All Units; Humboldt-Toiyabe National Forest All Units; Uinta-Wasatch-Cache All Units; Angeles National Forest All Units; Cleveland National Forest All Units; Eldorado National Forest All Units; Inyo National Forest All Units; Klamath National Forest All Units; Lassen National Forest All Units; Los Padres National Forest All Units; Mendocino National Forest All Units; Modoc National Forest All Units; Plumas National Forest All Units; San Bernardino National Forest All Units; Sequoia National Forest All Units; Shasta Trinity National Forest All Units; Sierra National Forest All Units; Tahoe National Forest All Units; Deschutes National Forest All Units; Fremont-Winema National Forest All Units; Gifford Pinchot National Forest All Units; Malheur National Forest All Units; Mt Baker-Snoqualmie National Forest All Units; Mt. Hood National Forest All Units; Ochoco National Forest All Units; Rogue River-Siskiyou National Forest All Units; Umatilla National Forest All Units; Umpqua National Forest All Units; Wallowa-Whitman National Forest All Units; Okanogan-Wenatchee National Forest All Units; Willamette National Forest All Units; R10 - Alaska Region All Units; WO - Washington Office - National headquarters |
Decision Memo · Clackamas River Ranger District · updated 6/25/2012
clackamas county oregon · Clackamas, Oregon
instalation of fiber optic line under roads from Ripplebrook to Highway 26
Special use management
Comment Period
04/28/2012
Decision
06/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District; Zigzag Ranger District |
Decision Memo · Zigzag Ranger District · updated 5/9/2012
Salmon River near Salmon River Road (Road 2618) near Zigzag, OR · Clackamas, Oregon
The purpose of this project is to reactivate a historic side channel at river mile 8.9 on the Salmon River to increase habitat complexity for the benefit of salmonid and riparian species.
Wildlife, fish, rare plants
Comment Period
04/07/2012
Decision
05/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Salmon River Side Channel 23a Restoration Decision Memo | Decision Signed Date: 05/09/2012 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Section 22, T. 3S, R. 7E |
Decision Memo · Hood River Ranger District · updated 3/26/2012
1700-680 road on Hood River Ranger District and 4431 road on Barlow Ranger District · Hood River; Wasco, Oregon
Cascade Huts operates three huts within the Mt Hood National Forest. An additional 2 huts would be added to its inventory available for rent in 2011.The huts are to be placed on existing roads. Proposed locations are the 1700-680 and 4431 Roads.
Special use managementRecreation management
Decision
03/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Cascade Huts LLC - Expansion of 2 Additional Huts | Decision Signed Date: 03/08/2012 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District; Hood River Ranger District |
| Legal Land Description | T1S, R10E, Section 34 and T2S, R11E, Section 5 |
Environmental Assessment · Barlow Ranger District · updated 3/26/2012
City of The Dalles Municipal Watershed · Hood River; Wasco, Oregon
Reduce hazardous fuels on approx 2400 acres within The Dalles Municipal Watershed. This project focuses on the interior of the watershed, including in-holdings. Activities may include commercial/sapling thinning, underburning, piling, and/or pruning.
Watershed managementFuels managementForest productsWildlife, fish, rare plants
Objection Period Start
09/06/2011
Decision
03/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Municipal Watersheds |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| The Dalles Watershed Phase II Hazardous Fuels Reduction | Decision Signed Date: 03/21/2012 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T1S and T2S, R10 E and R11E, Willamette Meridian |
Decision Memo · Zigzag Ranger District · updated 12/9/2011
Zigzag, Oregon · Clackamas, Oregon
This project proposes to expand and remodel the Zigzag Ranger District Office.
Facility management
Decision
06/2011 (Estimated)
Implementation
03/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Zizgag Ranger Station Office Expansion and Remodel | Decision Signed Date: 06/01/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
Decision Memo · Hood River Ranger District · updated 9/26/2011
Mt. Hood Meadows Ski Resort · Hood River, Oregon
Complete projects in the MHM ski permit area, including repairing ski trail signs, replacing sign posts, installing fiber optic cable/footings for lift ticket validation system, installing winch anchor, & installing two flumes for a water study.
Special use managementRecreation management
Decision
09/2011 (Estimated)
Implementation
09/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Mt. Hood Meadows Ski Resort 2011 Maintenance Projects | Decision Signed Date: 09/26/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T3S, R9E |
Decision Memo · Hood River Ranger District · updated 8/1/2011
Ghost Ridge area, near Cloud Cap Road (Forest Service Road 3512) · Hood River, Oregon
Install & maintain solar powered weather station in Ghost Ridge area, near Cloud Cap Road. Station requires: weather proof building, precipitation gage, antenna tower, snow pillow, solar panels, air temp/pressure sensors, wind gage, and fencing.
Special use managementLand ownership management
Decision
07/2011 (Estimated)
Implementation
07/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Cloud Cap RAWS Project | Decision Signed Date: 07/28/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T2S, R9E, Section 10 |
Decision Memo · Hood River Ranger District · updated 6/17/2011
Laurenace Lake and Settling pond approximately seven miles SW of Parkdale, Oregon · Hood River, Oregon
Three projects would be completed by MFID within the permit area: Eliot Irrigation Ditch Tree Removal, Flow Meter Installation, & Water Level Monitoring Device Installation. A fourth project (PIT Tag Antennas) would be completed by the USFS.
Special use managementFacility managementWatershed management
Decision
06/2011 (Estimated)
Implementation
07/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Watershed Improvements |
| Middle Fork Irrigation District 2011 Projects | Decision Signed Date: 06/01/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1S, R9E, Sections 23, 26, 27, and 28 |
Decision Memo · Hood River Ranger District · updated 5/6/2011
Settling pond approximately six miles SW of Parkdale, Oregon · Hood River, Oregon
MFID proposes to install 500 of 18-inch HDPE pipe in the upper Glacier ditch on National Forest Lands. This is part of a larger project that will pipe approximately 10,000 feet of Glacier ditch.
Special use managementFacility management
Decision
05/2011 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Watershed Improvements |
| Glacier Ditch Piping Decision Memo | Decision Signed Date: 05/06/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1N, R9E, Section 23 |
Decision Memo · Mt. Hood National Forest All Units · updated 3/31/2011
Campgrounds and day use areas across the Forest. · Clackamas; Hood River; Marion; Wasco, Oregon
Issue a temporary, one year, special use permit for recreation sites that are currently managed by the Forest Service.
Facility managementRecreation managementSpecial use management
Decision
03/2011 (Estimated)
Implementation
03/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations; Facility Maintenance |
| Temporary Concessionaire Permit Memo | Decision Signed Date: 03/20/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Forest-wide |
Decision Memo · Mt. Hood National Forest All Units · updated 3/25/2011
Campgrounds and day use areas across the Forest. · Clackamas; Hood River; Marion; Wasco, Oregon
Reissue campground concessionaire permits for sites that have been managed under concessionaire permits for an additional 10-year term.
Special use managementFacility managementRecreation management
Decision
03/2011 (Estimated)
Implementation
03/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations; Facility Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Forest-wide |
Environmental Assessment · Clackamas River Ranger District · updated 3/22/2011
Several high elevation areas on the Mt. Hood Forest · Clackamas, Oregon
thinning second growth stands to get more sunlight to understory huckleberries.
Forest products
Comment Period
06/06/2010
Decision
03/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Dispersed Recreation Mgmt.; Species Habitat Improvements; Timber Sales (Green) |
| Huckleberry Enhancement Decision Notice | Decision Signed Date: 03/14/2011 Legal Notice Date: 03/16/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District; Zigzag Ranger District |
Environmental Assessment · Clackamas River Ranger District · updated 3/17/2011
The majority of project activities would occur in the Collawash River watershed. · Clackamas, Oregon
Decommissioning roads to improve hydrologic function and reduce adverse impacts to aquatic and terrestrial habitats on the Clackamas River Ranger District.
Road managementWildlife, fish, rare plantsWatershed management
Comment Period
11/16/2010
Decision
03/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning |
| Clackamas Road Decommissioning for Habitat Restoration, Increment 2 | Decision Signed Date: 03/16/2011 Legal Notice Date: 03/17/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
Environmental Assessment · Hood River Ranger District · updated 3/2/2011
Mt. Hood Meadows Ski Resort · Hood River, Oregon
1) Replace & upgrade Stadium Chair Lift; 2) Restore wetland at the base on the existing lift; 3) Restore approx 1 acre of wetland between the Blue and Mt Hood Express chairlifts; 4) Replace the culvert on the North service road to allow debris flow.
Special area managementRecreation managementWildlife, fish, rare plants
Comment Period
01/10/2011
Decision
03/2011 (Estimated)
Implementation
03/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Mt. Hood Meadows Ski Resort Enhancements | Decision Signed Date: 03/02/2011 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T2S, R9E |
Decision Memo · Hood River Ranger District · updated 1/6/2011
Upslope of Forest Service Road 1640 · Hood River, Oregon
Construct a trench to facilitate conducting geologic research on fault scarps. Trench is approx 100-ft long by 10-ft wide by 15-ft deep. The trench would be open for 2-3 weeks. The site would be restored after the research is completed.
Special use managementMinerals and geology
Decision
01/2011 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | NW ¼ of SE ¼ of Section 18, T1S, R9E |
Decision Memo · Barlow Ranger District · updated 11/24/2010
Skyline Sno Park · Wasco, Oregon
There are inadequate toilet facilities at Skyline Sno-park to accommodate weekend use. The project proposal is to install another vault toilet next to the existing toilet. The proposed site is in a graveled, compacted old road bed.
Recreation management
Decision
11/2010 (Estimated)
Implementation
11/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Skyline Toilet Installation | Decision Signed Date: 11/17/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T4S, R9E, Section 33 |
Decision Memo · Hood River Ranger District · updated 11/19/2010
Cloud Cap Road (Forest Service Road 3512) · Hood River, Oregon
Remove felled trees within 100-feet of Cloud Cap Road. The equipment would remain in road prism, and would swing logs onto trucks or pull logs with cable and picked them up with grapples. Logs would be stored for future aquatic restoration projects.
Wildlife, fish, rare plantsWatershed management
Decision
02/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Species Population Enhancements; Watershed Improvements |
| Cloud Cap Road Tree Removal and Native Vegetation Planting for Gnarl Ridge | Decision Signed Date: 02/05/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T2S, R9E, Sections 10 and 11 |
Decision Memo · Hood River Ranger District · updated 9/29/2010
Laurance Lake, approximately seven miles SW of Parkdale, Oregon · Hood River, Oregon
Remove approximately 30 trees from the south Clear Branch Dam abutment and add riprap to the upstream (west) face of the dam as per FERC directive to improve dam integrity and safety.
Special use managementFacility management
Decision
09/2010 (Estimated)
Implementation
10/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Middle Fork Irrigation District 2010 Maintenance Projects | Decision Signed Date: 09/27/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1N, R9E, Section 27 |
Decision Memo · Hood River Ranger District · updated 9/28/2010
Near Laurance Lake, approximately seven miles SW of Parkdale, OR · Hood River, Oregon
Middle Fork Irrigation District will be conducting 2 maintenance projects on the Eliot Irrigation Ditch. Project #1 will replace a flushing gate with a hand-operated metal gate and project #2 will install a Powder River gate on the ditch access path.
Special use management
Decision
09/2010 (Estimated)
Implementation
10/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Middle Fork Irrigation District 2010 Maintenance Projects | Decision Signed Date: 09/27/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1N, R9E, Section 27 |
Environmental Assessment · Barlow Ranger District · updated 9/28/2010
Perimeter roads around and major interior roads within The Dalles Municipal Watershed · Hood River; Wasco, Oregon
Fuelbreak around the perimeter and on major interior roads of the City of The Dalles Municipal Watershed. The proposal is a result of a collaborative effort.
Fuels management
Objection Period Start
04/05/2006
Decision
06/2007 (Estimated)
Implementation
10/2007 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Municipal Watersheds; Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District; Hood River Ranger District |
| Legal Land Description | T1S, R11E sec. 18, 31, 29, 32, 21, R1S, R10E sec. 13, 14, 15, 22, 23, 27, 34 |
Decision Memo · Barlow Ranger District · updated 9/28/2010
Highway 216 in Maupin, Oregon (Junction of Highways 26 and 216) · Jefferson, Oregon
At junction of Hwy 26 and 216, demo an existing duplex, large garage and washroom building. Buildings would be replaced with two new single family dwellings with detached garages in approximately the same location. See supporting documents for maps.
Special use management
Decision
09/2010 (Estimated)
Implementation
09/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T5S, R10E, Section 18, Lot 8 |
Environmental Assessment · Barlow Ranger District · updated 9/3/2010
Ramsey and Fifteenmile Purchase Units · Wasco, Oregon
Reduce hazardous fuel loadings and ladder fuels, and change existing fire condition class in the area of Sportsman's Paradise Wildland Urban Interface (WUI), using input from the collaborative groups. Collaboration scheduled to begin in July 2008.
Fuels managementVegetation management (other than forest products)
Objection Period Start
12/11/2009
Decision
08/2010 (Estimated)
Implementation
03/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Sportsman’s Paradise Hazardous Fuels Reduction Project | Decision Signed Date: 08/26/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T2S, R12E, Sections 3, 7-10, 17-20 |
Environmental Impact Statement · Mt. Hood National Forest All Units · updated 8/27/2010
Forestwide · Clackamas; Hood River; Jefferson; Marion; Multnomah; Wasco, Oregon
To comply with Final Travel Managemet Rule [FR, Vol 70, No. 216 (2005)] for Off-highway vehicles. Designation of roads & trails open to OHV use by vehicle class. To amend the Forest Plan to change current policy closed to OHV unless designated open.
Road managementRecreation management
NOI in Federal Register
08/31/2007
DEIS NOA in Federal Register
08/28/2009
FEIS NOA in Federal Register
08/27/2010
Decision
08/2010 (Estimated)
Implementation
09/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Plan Amendment; Trail Management; Travel Management |
| Off-Highway Vehicle Management Plan, including Forest Plan Amendment #17 | Decision Signed Date: 08/16/2010 Legal Notice Date: 08/27/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
Decision Memo · Zigzag Ranger District · updated 8/10/2010
Forest Road 2612 near Rhododendron, Oregon · Clackamas, Oregon
A landslide obliterated a 200 foot section of Forest Road 2612. The project will repair the road at the slide site.
Road management
Decision
07/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Still Creek Road 2612 Slide Repair | Decision Signed Date: 07/27/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
Decision Memo · Zigzag Ranger District · updated 8/6/2010
2.5 miles SE of Rhododendron, OR near Forest Road 35B · Clackamas, Oregon
Authorize the construction of an access/egress driveway to an Organization Camp (Post Office Club) cabin which is location on National Forest System land.
Land ownership managementRecreation managementRoad management
Decision
08/2010 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Road Improvements/Construction |
| Portland Post Office Community Club Driveway Relocation | Decision Signed Date: 08/04/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S, R8E, Section 18 |
Decision Memo · Clackamas River Ranger District · updated 7/19/2010
wide spread accross the Clackamas River and Zigzag Ranger Districts · Clackamas; Marion; Multnomah; Wasco, Oregon
precommercial thinning of plantations on the Clackamas River and Zigazag Ranger Districts
Vegetation management (other than forest products)
Decision
04/2010 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District; Zigzag Ranger District |
Decision Memo · Barlow Ranger District · updated 6/27/2010
Ramsey Creek at River Mile 7.5 · Wasco, Oregon
Restore stream habitat connectivity in Ramsey Creek drainage for steelhead trout and interior redband trout. Project would remove two cement headwalls from the stream channel that are juvenile salmonid fish barrier.
Wildlife, fish, rare plantsWatershed management
Decision
06/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Ramsey Creek Fish Passage Enhancement | Decision Signed Date: 06/07/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T2S, R12E, Section 7 |
Decision Memo · Zigzag Ranger District · updated 6/17/2010
Junction of state Highway 6 and Road 173, Government Camp, OR · Clackamas, Oregon
Construct a landmark sign at the junction of Highway 26 and Timberline Road (Rd. 173) to help visitors find Timberline Lodge.
Road managementFacility managementRecreation management
Decision
07/2009 (Estimated)
Implementation
07/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S, R9E, Section 24 |
Decision Memo · Hood River Ranger District · updated 6/10/2010
Bennett Pass · Hood River, Oregon
Install at 180-foot black monopole cell tower to serve north Highway 35 and Mt. Hood Meadows Ski Resort. Capable of handling 2 to 3 co-locators (e.g., Hood River Sheriff's Office). Buried powerline from the Mt. Hood Meadows overpass.
Special use management
Decision
04/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Bennett Pass Cellular Tower Installation | Decision Signed Date: 04/13/2010 Legal Notice Date: 04/13/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T3S, R9E, Section 14 |
Decision Memo · Hood River Ranger District · updated 6/3/2010
Hood River and Barlow Ranger Districts · Hood River; Wasco, Oregon
Hood River and Barlow Districts propose to precommerical thin (PCT) approximately 15,000 acres of young (10-30 year old), overstocked plantations. PCT is completed by hand crews with chainsaws cutting down trees less than 6-inches in diameter.
Vegetation management (other than forest products)Wildlife, fish, rare plants
Decision
04/2010 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Sapling Thinning Decision Memo | Decision Signed Date: 04/07/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District; Hood River Ranger District |
Decision Memo · Barlow Ranger District · updated 6/3/2010
White River 5th Field Watershed (HUC #1707030609) · Wasco, Oregon
Protect three small sensitive spring/wetland areas from over utilization by livestock in the White River Grazing Allotment by placing a four strand barbwire (wildlife fence) or buck-n-pole fence. Fences would be built by hand.
Watershed managementGrazing managementWildlife, fish, rare plants
Decision
06/2010 (Estimated)
Implementation
06/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management; Species Habitat Improvements; Rangeland Vegetation Improvements; Watershed Improvements |
| White River Wetland Fencing Decision Memo | Decision Signed Date: 06/01/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T5S, R10E, Sections 7, 9, and 17 |
Environmental Impact Statement · Zigzag Ranger District · updated 4/19/2010
Timberline Ski Area · Clackamas, Oregon
Construction of a new chairlift and ski trail network in the southwest corner of Timberline Ski Area permit area.
Special use management
NOI in Federal Register
07/18/2002
DEIS NOA in Federal Register
03/25/2005
FEIS NOA in Federal Register
11/25/2005
Decision
11/2005 (Estimated)
Implementation
07/2006 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Timberline Express Chairlift ROD | Decision Signed Date: 11/01/2005 Legal Notice Date: 12/01/2005 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | R 9E, T 3S, Section 7 |
Decision Memo · Hood River Ranger District · updated 3/31/2010
Middle Fork Hood River Bridge on Forest Service Road 16 · Hood River, Oregon
Flooding in 2006 washed out the bridge over the Middle Fork of Hood River (Red Hill Drive Bridge). The proposed project will replace the bridge. The bridge will be designed to sustain future flood events.
Decision
02/2010 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1N, R10E, Section 31 |
Environmental Assessment · Clackamas River Ranger District · updated 3/30/2010
Clackamas River Ranger District, Mt. Hood National Forest · Clackamas, Oregon
Decommissioning roads to improve hydrologic function and reduce adverse impacts to aquatic and terrestrial habitats in the Upper Clackamas area.
Watershed managementWildlife, fish, rare plants
Comment Period
03/21/2009
Decision
05/2009 (Estimated)
Implementation
07/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning |
| Clackamas Road Decommissioning for Habitat Restoration | Decision Signed Date: 05/08/2009 Legal Notice Date: 05/08/2009 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | District-wide |
Decision Memo · Hood River Ranger District · updated 3/30/2010
Cloud Cap Road - Gnarl Ridge Fire Area · Hood River, Oregon
Plant approximately 300 acres in the severely burned area from Gnarl Ridge Fire with native tree species, native shrub and grass species to restore the native ecosystem and minimize soil erosion. Project is outside designated or proposed wilderness.
Vegetation management (other than forest products)Watershed management
Decision
02/2010 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (11), 36 Cfr 220.6(E)(11) |
| Special Authority | National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T2S, R9E, Sec10 |
Environmental Assessment · Hood River Ranger District · updated 3/19/2010
The Mill Creek planning area includes the North Fork of Mill Creek and small portions of Mosier and Neal Creeks, approx. 5 miles southeast of the community of Mt. Hood · Hood River; Wasco, Oregon
The project is a collaborative approach to fuels reduction and restoration in the North Fork Mill, Mosier, and West Fork Neal watersheds. It includes timber harvest, road closures/decommission, road management, restoration, and fuels reduction.
Wildlife, fish, rare plantsRoad managementVegetation management (other than forest products)Forest productsFuels managementRecreation management
Objection Period Start
07/31/2008
Decision
12/2008 (Estimated)
Implementation
06/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface; Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Trail Management; Road Improvements/Construction; Travel Management; Timber Sales (Green); Watershed Improvements |
| North Fork Mill Creek | Decision Signed Date: 12/19/2008 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1S-T2S, R10E-R11E, WM |
Environmental Assessment · Zigzag Ranger District · updated 12/18/2009
National Forest System Lands near Rhododendron, Oregon · Clackamas, Oregon
Reissuance of Special Use Permit for recreation residences (summer homes)
Recreation management
Comment Period
06/23/2009
Decision
12/2009 (Estimated)
Implementation
01/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Land Use Adjustments; Developed Site Management; Harzardous Waste Compliance Actions; Heritage Resource Management; Special Use Authorizations; Facility Maintenance |
| Cool Creek Recreational Residence Tract | Decision Signed Date: 12/16/2009 Legal Notice Date: 12/18/2009 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T.3S., R.7E., and T.3S., R.8E., WM, Clackamas County, Oregon |
Decision Memo · Zigzag Ranger District · updated 12/18/2009
Timberline Ski Area · Clackamas, Oregon
The current water supply line to the lodge was installed in 1962 and has outlived its design life. It is leaking; has high maintenance needs; and will likely fail in the near future. A new modern water line in needed to provide reliable water.
Facility managementHeritage resource management
Decision
12/2009 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Heritage Resource Management; Facility Maintenance |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
Decision Memo · Hood River Ranger District · updated 12/3/2009
Project is at the base of Mt. Hood on the northeast side. It is in the East Fork Hood River watershed about 2 miles from Oregon State Hwy 35 near the Cooper Spur Ski Area. · Hood River, Oregon
This project is a collaborative effort to identify possible fuels reduction activities on 30 acres in and around the wildland-urban interface around Cooper Spur. Activities could include thinning, fuelbreaks, and/or prescribed burning.
Fuels managementVegetation management (other than forest products)Forest products
Comment Period
12/10/2007
Decision
04/2008 (Estimated)
Implementation
06/2008 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Salvage) |
| DB Cooper Fuels Reduction Demonstration Project | Decision Signed Date: 04/11/2008 Legal Notice Date: 04/15/2008 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1S & T2S, R9E & R10E, Willamette Meridian |
Environmental Assessment · Hood River Ranger District · updated 9/21/2009
Lake Branch Watershed on the Hood River Ranger District · Hood River, Oregon
Thinning of 2,163 acres of second-growth plantations. Includes thinning in matrix and riparian reserves.
Forest productsWildlife, fish, rare plants
Comment Period
07/02/2009
Decision
09/2009 (Estimated)
Implementation
10/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| Lake Branch Thinning | Decision Signed Date: 09/21/2009 Legal Notice Date: 09/21/2009 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T1N, R8E; T1S, R8E; Willamette Meridian |
Environmental Assessment · Clackamas River Ranger District · updated 9/18/2009
Clackamas River Ranger District, Mt. Hood National Forest · Clackamas, Oregon
District-wide restoration project including side channels along rivers for better fish habitat, improve fish passage at culverts, road closures, and restoration of unauthorized shooting damage. Includes CFR closure for shooting.
Watershed managementWildlife, fish, rare plants
Comment Period
04/30/2009
Decision
06/2009 (Estimated)
Implementation
10/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Maintenance; Road Improvements/Construction; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | District-wide |
Decision Memo · Hood River Ranger District · updated 9/18/2009
Mt. Hoood Meadows Ski Resort · Hood River, Oregon
Proposal by Mt Hood Meadows Ski Resort to pave the Annex parking lot, add bioswales for stormwater treatment and to protect Mitchell Creek, and restore a small wetland in the southwest corner of the lot.
Special use managementWildlife, fish, rare plantsRecreation management
Decision
07/2009 (Estimated)
Implementation
07/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Mt. Hood Meadows Annex Parking Lot Paving and Wetland Restoration | Decision Signed Date: 07/14/2009 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
Environmental Assessment · Clackamas River Ranger District · updated 3/24/2009
On the Clackamas River Ranger District · Clackamas, Oregon
Thinning of 2,175 acres of stands that have already been thinned once and are now ready for a second thinning. Includes thinning in matrix, riparian reserves and late-successional reserves.
Forest productsWildlife, fish, rare plants
Comment Period
10/02/2008
Decision
03/2009 (Estimated)
Implementation
07/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | T.4S., R.5E.; T.4S, R.6E., T.5S., R.7E.; T.6S., R.6E., T.7S., R.6E.; T.6S., R.7E.; T.6S., R.8E.; Willamette Meridian |
Decision Memo · Zigzag Ranger District · updated 3/23/2009
Forest road 1828, Mt. Hood National Forest, Zigzag Ranger District · Clackamas, Oregon
Forest Road 1828 was damaged during the fall flood of 2006. The proposed project consists of long-term repairs to flood damaged sections of the road.
Road managementWatershed managementRecreation management
Decision
03/2009 (Estimated)
Implementation
07/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction; Travel Management; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
Environmental Assessment · Mt. Hood National Forest All Units · updated 3/20/2009
Barlow, Hood River, and Zigzag Ranger Districts · Clackamas; Hood River, Oregon
In order to improve hydrologic function and reduce adverse impacts to aquatic habitat, this project proposes to decommission unneeded roads in several priority sixth-field subwatersheds.
Wildlife, fish, rare plantsWatershed management
Comment Period
10/17/2008
Decision
12/2008 (Estimated)
Implementation
05/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District; Hood River Ranger District; Zigzag Ranger District |
Environmental Assessment · Detroit Ranger District · updated 12/16/2008
The Bethel-Round Butte transmission line crosses lands on the Willamette, Mt. Hood, and Ochoco NFs beginning on the Warm Springs Reservation. · Clackamas; Marion, Oregon
Authorize a special use permit for Portland General Electric to continue to operate electrical tranmission lines across National Forest lands on the Willamette, Mt. Hood, and Ochoco National Forests.
Special use management
Comment Period
11/07/2008
Decision
12/2008 (Estimated)
Implementation
01/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| PGE Special Use Permit | Decision Signed Date: 12/15/2008 |
| Forests | Mt. Hood National Forest; Ochoco National Forest; Willamette National Forest |
| Districts | Clackamas River Ranger District; Prineville Ranger District; Detroit Ranger District |
| Legal Land Description | T9S, R5,6,7,8E, multiple sections |
Environmental Assessment · Zigzag Ranger District · updated 9/30/2008
Forest Road 1825, Mt. Hood National Forest, Zigzag Ranger District · Clackamas, Oregon
The bridge on Forest Road 1825 was damaged during the fall flood of 2006. The proposed project would repair or replace the damaged bridge.
Watershed managementRecreation managementRoad management
Scoping Start
01/2008 (Estimated)
Comment Period
01/2008 (Estimated)
Decision
12/2008 (Estimated)
Implementation
06/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Maintenance; Road Improvements/Construction; Travel Management; Watershed Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
Environmental Assessment · Clackamas River Ranger District · updated 9/30/2008
On the Clackamas River Ranger District in the Upper Clackamas Watershed. · Clackamas, Oregon
Thinning of 1,094 acres of second-growth plantations. Includes thinning in matrix, riparian reserves and late-successional reserves.
Forest productsWildlife, fish, rare plants
Comment Period
04/15/2008
Decision
08/2008 (Estimated)
Implementation
10/2008 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | The project is located in T.6S., R.6E.; T.6S., R.7E., T.7S., R.7E.; T.8S., R.7E.; T.7S., R.8E.; Willamette Meridian |
Environmental Assessment · Barlow Ranger District · updated 3/26/2008
T2S, R11E, Sec. 7,8,14,15,16,17,18 · Wasco, Oregon
Reduce hazardous fuel loadings and ladder fuels, and change the existing fire condition class in the area of Camp Baldwin Boy Scout Camp Wildland Urban Interface (WUI), using the Boy Scouts and other groups as collaborators.
Fuels managementLand management planning
Objection Period Start
09/12/2007
Decision
01/2008 (Estimated)
Implementation
01/2008 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (10) |
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |