This project will conduct activities to install a solar panel array and components at the A-Frame site at Lost Lake Campground. This will provide a safer and more efficient lighting system for recreationists.
Location
A Frame at Lost lake Campground
Project timeline
1
Scoping Start
03/01/2022
2
Decision
05/2022 (Estimated)
3
Implementation
05/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations; Facility Maintenance |
| Decision Decided Date | 05/24/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |