Middle Fork Irrigation District proposes to construct a roughened channel at two existing partial fish passage barriers. Large boulders would be added to the channel below the existing boulder weirs to create a steep riffle that is passable by fish.
Location
Coe Branch Adjacent to the Middle Fork Irrigation District Coe Branch Irrigation Diversion
Project timeline
1
Scoping Start
08/26/2013
2
Comment Period
08/29/2013
3
Decision
10/2013 (Estimated)
4
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Special Use Authorizations; Watershed Improvements |
| Middle Fork Irrigation District Coe Branch Diversion Grade Control Project | Decision Signed Date: 10/01/2013 Legal Notice Date: 10/22/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T1S, R9E, Section 27 |