Restore specific high priority watersheds that have been identified through Watershed Restoration Action Plans as well as other high priority restoration projects outside these watersheds.
Location
Still Creek, Salmon River, Hood River, Fifteenmile, and Clackamas River watersheds.
Project timeline
1
Scoping Start
10/17/2012
2
Comment Period
03/15/2013
3
Decision
04/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Dispersed Recreation Mgmt.; Species Habitat Improvements; Species Population Enhancements; Road Maintenance; Watershed Improvements |
| Forestwide Restoration Decision Memos (3) | Decision Signed Date: 04/23/2013 Legal Notice Date: 04/26/2013 |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |