This project will remove a tree-damaged toilet and install a new toilet in the same location at the Eightmile Day Use Area.
Location
Eightmile Day Use Area
Project timeline
1
Scoping Start
05/04/2021
2
Decision
07/2021 (Estimated)
3
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 07/21/2021 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.2.S., R.10.E., section 8 |