The project proposes to complete aquatic restoration activities for instream and floodplain restoration across the forest.
Location
Across the Mt. Hood National Forest where instream and floodplain restoration needs are identified.
Project timeline
1
Scoping Start
01/10/2018
2
Decision
05/2018 (Estimated)
3
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Mt. Hood Instream and Floodplain Restoration | Decision Signed Date: 05/18/2018 |
| Forests | Mt. Hood National Forest |
| Districts | Mt. Hood National Forest All Units |
| Legal Land Description | Not Applicable |