This project will replace a bridge on the Dog River Trail at the Puppy Creek crossing.
Location
The project is located at the intersection of the Dog River Trail (#675) and Puppy Creek.
Project timeline
1
Scoping Start
10/18/2022
2
Decision
10/2022 (Estimated)
3
Implementation
10/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Trail Management |
| Decision Decided Date | 10/24/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.1 S., R.10 E., Section 21 |