A portion of Forest Service road 20e is no longer useable for accessing Lady Creek Water System's pressure station; therefore, there is a need to repair this road. Also, there is a need to replace unserviceable buried water pipes near the road.
Location
Section 14, T3S, R7E
Project timeline
1
Scoping Start
05/01/2025
2
Decision
05/2025 (Estimated)
3
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Maintenance |
| Lady Creek Road Repair and Pipe Replacement | Decision Signed Date: 05/15/2025 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | Not Applicable |