This project analyzes a combination of proposals from Cascade Utilities for installing new fiber optic line within road rights of way and existing utility corridors.
Location
Mt. Hood National Forest, Clackamas River, Zigzag and Hood River Ranger Districts within existing utility corridors and/or road rights-of-way.
Project timeline
1
Scoping Start
01/20/2017
2
Decision
03/2017 (Estimated)
3
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Cascade Utilities Fiber Optic Line Installation | Decision Signed Date: 03/15/2017 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District; Hood River Ranger District; Zigzag Ranger District |
| Legal Land Description | T3SR8.5ESec.24 and 25 and T3SR9ESec. 30 and 31. T4SR9ESec. 6, 7, 8, 17, and 20. T3SR9E Sec. 3. T5S, R6E, Sec. 34, and T6S, R6E, Sec. 3, and T6S, R6E, Sec. 2. T6S, R6E, Sec. 2. |