In order to provide safe and reliable power, PGE has proposed to replace a current buried powerline that is failing due to aging. This new line (about 1,300 feet in length) will be installed adjacent to the existing line, which will remain in ground.
Location
The proposed replacement powerline is near the Summit Ski Area.
Project timeline
1
Scoping Start
06/29/2015
2
Decision
09/2015 (Estimated)
3
Implementation
09/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Portland General Electric (PGE) Buried Line Replacement near Summit Ski Area CE | Decision Signed Date: 09/04/2015 |
| Forests | Mt. Hood National Forest |
| Districts | Zigzag Ranger District |
| Legal Land Description | T3S R8E Section SW13 and NW24 |