There are inadequate toilet facilities at Skyline Sno-park to accommodate weekend use. The project proposal is to install another vault toilet next to the existing toilet. The proposed site is in a graveled, compacted old road bed.
Location
Skyline Sno Park
Project timeline
1
Scoping Start
10/20/2009
2
Decision
11/2010 (Estimated)
3
Implementation
11/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Skyline Toilet Installation | Decision Signed Date: 11/17/2010 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T4S, R9E, Section 33 |