Assessment of options to deal with removing hazard trees caused by root diseases in Indian Henry Campground and modernization of facilities. Most of campground is closed at this time due to hazard.
Location
Indian Henry Campground
Project timeline
1
Scoping Start
09/01/2013
2
Comment Period
07/2015 (Estimated)
3
Objection Period Start
11/2015 (Estimated)
4
Decision
03/2016 (Estimated)
5
Implementation
03/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Timber Sales (Green) |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |