This project will create a staging area approximately one acre in size to facilitate pipeline replacement activities.
Location
Approixmately one acre adjacent to NFS Road 1700690
Project timeline
1
Scoping Start
09/02/2022
2
Decision
11/2022 (Estimated)
3
Implementation
04/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Dog River Pipeline Staging Area | Decision Signed Date: 11/29/2022 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T.2S., R.10E., S.3 |