Remove failing shelter and replace it with a new prefabricated shelter; conduct road maintenance as needed to complete replacement of shelter.
Location
Clear Lake Butte, south of Clear Lake.
Project timeline
1
Scoping Start
08/18/2020
2
Decision
11/2020 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Road Maintenance |
| Decision Decided Date | 11/06/2020 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.4S.; R.9E.;section 7 |