Decision Memo Completed

Mill Creek Repeater Site Shelter Replacement

Mt. Hood National Forest Hood River, Oregon Mt. Hood National Forest All Units

Remove failing shelter and replace it with a new prefabricated shelter; conduct road maintenance as needed to complete replacement of shelter.

Location

Mill Creek Buttes Repeater Site

Project timeline

1
Scoping Start
11/12/2019
2
Decision
12/2019 (Estimated)
3
Implementation
05/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3); 32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Maintenance; Road Maintenance
Decision Decided Date12/06/2019
ForestsMt. Hood National Forest
DistrictsBarlow Ranger District
Legal Land DescriptionT. 1 S., R. 10 E., section 34
Road managementFacility management