Remove failing shelter and replace it with a new prefabricated shelter; conduct road maintenance as needed to complete replacement of shelter.
Location
Mill Creek Buttes Repeater Site
Project timeline
1
Scoping Start
11/12/2019
2
Decision
12/2019 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3); 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance; Road Maintenance |
| Decision Decided Date | 12/06/2019 |
| Forests | Mt. Hood National Forest |
| Districts | Barlow Ranger District |
| Legal Land Description | T. 1 S., R. 10 E., section 34 |