Construct a waterline from Coe Creek to the Middle Fork Irrigation District (MFID) settling pond to improve water quality for the community served by MFID and reduce impacts of sedimentation on existing equipment operated by MFID and MFID customers.
Location
Project activities will take place between the existing connection of the Laurence Lake waterline and the existing Coe Creek waterline, and the existing sediment basin.
Project timeline
1
Scoping Start
10/14/2019
2
Decision
11/2019 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Middle Fork Irrigation District Coe Water Pipeline Project | Decision Signed Date: 11/22/2019 |
| Forests | Mt. Hood National Forest |
| Districts | Hood River Ranger District |
| Legal Land Description | T.1S.,R.9E.,S.27 |