Project timeline

1
Scoping Start
10/14/2019
2
Decision
11/2019 (Estimated)
3
Implementation
06/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Special Use Authorizations; Facility Maintenance
Middle Fork Irrigation District Coe Water Pipeline ProjectDecision Signed Date: 11/22/2019