Chelan County Public Utility District proposes to build a new electrical transmission line to serve the Entiat Valley.
Location
Along the existing BPA powerline from Earthquake Point to Crum Canyon.
Project timeline
1
Scoping Start
06/16/2007
2
Comment Period
06/19/2008
3
Decision
09/2008 (Estimated)
4
Implementation
06/2009 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Entiat Valley 115 kV Transmission Program | Decision Signed Date: 09/10/2008 Legal Notice Date: 09/17/2008 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Entiat Ranger District |
| Legal Land Description | T26N, R20E, Sections 25, 26, 27, 28, 33, 36; T26N, R21E, Sections 31, 32, 33 |