Treat stands within wildland urban interface to reduce tree density and spruce budworm affected trees.
Location
Swauk Watershed
Project timeline
1
Scoping Start
11/01/2003
2
Objection Period Start
08/07/2009
3
Decision
09/2009 (Estimated)
4
Implementation
11/2009 (Estimated)
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Green) |
| Liberty Fuels II Project | Decision Signed Date: 09/18/2009 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Cle Elum Ranger District |
| Legal Land Description | Section 18 & 31, T. 21N., R.18E., Sections 5, 6, & 36 T.21N., R.17E., WM |