Decision Memo Completed

Benton Rural Electric Associations (Benton REA) Clear Creek Rebuild Project

Okanogan-Wenatchee National Forest Yakima, Washington Naches Ranger District

Rebuild the powerline which begins approximately 1 mile west from the intersection of Clear Lake Road 1200-840 and the 1200 road. The projet area spans west past the end of the road and across Clear Creek.

Location

Clear Creek west of Clear Lake, Naches Washington

Project timeline

1
Scoping Start
07/23/2013
2
Decision
08/2014 (Estimated)
3
Implementation
08/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Benton REA Clear Creek Line Rebuild Decision MemoDecision Signed Date: 08/07/2014
ForestsOkanogan-Wenatchee National Forest
DistrictsNaches Ranger District
Legal Land DescriptionT. 13 N., R. 12 E., Sections 2-4.
Special use management