Rebuild the powerline which begins approximately 1 mile west from the intersection of Clear Lake Road 1200-840 and the 1200 road. The projet area spans west past the end of the road and across Clear Creek.
Location
Clear Creek west of Clear Lake, Naches Washington
Project timeline
1
Scoping Start
07/23/2013
2
Decision
08/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Benton REA Clear Creek Line Rebuild Decision Memo | Decision Signed Date: 08/07/2014 |
| Forests | Okanogan-Wenatchee National Forest |
| Districts | Naches Ranger District |
| Legal Land Description | T. 13 N., R. 12 E., Sections 2-4. |